Document Type: Government Resolution (GR) — Administrative Sanction for Public Works Project
Reference Number: GR No. BGT-1009/Pr.Cr.10/RAUSH-1, dated 10 June 2022
Issued By: Government of Maharashtra, Home Department (गृह विभाग)
Effective Date: 10 June 2022 (from date of publication on www.maharashtra.gov.in)
Digital Reference Code: 202206101255311129
This GR grants revised administrative sanction for the construction of a new building (Excise Bhavan) for the State Excise Department at Boribunder, Mumbai. The original estimated cost of ₹5,183.41 lakh has been revised to ₹6,936.23 lakh due to an increase of ₹1,752.82 lakh from the Chief Engineer, Public Works Department (Regional Division), Mumbai. The project is funded under the Public Works Capital expenditure budget head and has been approved by both the High-Power Committee chaired by the Chief Secretary (24.02.2022) and the Finance Department's Expenditure Priorities Committee chaired by the Deputy Chief Minister (13.05.2022).
Project Details:
Cost Breakdown (Revised Administrative Sanction):
| Component | Amount (₹) |
|---|---|
| A. Building Construction (including contingencies) | |
| - Original items | 33,57,00,962.91 |
| - New items | 6,06,26,688.15 |
| A Total | 39,63,27,351.07 |
| B. Electrical | |
| - Original items | 10,32,60,926.00 |
| - New items | 2,25,74,709.00 |
| B Total | 12,58,35,635.00 |
| C. Water Supply | — |
| Subtotal (A + B + C) | 52,21,62,986.07 |
| MCGM Charges | 3,18,48,676.00 |
| Contingencies | 1,64,12,542.00 |
| Price Escalation | 4,92,21,871.00 |
| Insurance | 29,48,051.00 |
| Service Tax/GST | 3,18,24,085.00 |
| GST 2022 (on balance work) | 3,92,04,909.00 |
| GRAND TOTAL | ₹69,36,23,120.07 |
| (In Lakhs) | ₹6,936.23 lakh |
Budget Head for Funding:
Conditions and Compliance Requirements:
Implementation Standards:
Scope of Sanction: