This Government Resolution grants administrative sanction for the construction of an administrative office building for the Superintendent of State Excise, Jalna (अधीक्षक, राज्य उत्पादन शुल्क, जालना). The total approved cost is ₹8,62,96,191 (Eight Crore, Sixty-Two Lakh, Ninety-Six Thousand, One Hundred and Ninety-One only) based on 2019-20 budget provisions. The sanction is issued under the control of the Principal Secretary, State Excise, and the funds will be drawn from the Major Head "4059 — Public Works Overhead Capital (15) Prohibition and State Excise, (15)(01) Major Works (Scheme) (4059-1033-53 Major Works."
Administrative Approval:
Funding Source:
Building Specifications (from Estimate Sheet):
Project Components (Essential Items):
| Sr. No. | Component | Specification | Cost (₹) |
|---|---|---|---|
| 1(a) | Building Proper (Built-Up Area) | Basement + GF + 1st Floor = 1,052.76 Sqm | 3,32,29,317 |
| 1(b) | Fuel Gas Pipeline | Lump sum | 0 |
| 1(c) | Bio Digester | Lump sum | 0 |
| 1(d) | Rain/Roof Water Harvesting | 526.38 Sqm @ ₹800/Sqm | 4,21,104 |
| 1(e) | Solar Rooftop (MoU to be executed) | Lump sum | 30,00,000 |
| 1(f) | Ramp for Handicaps | Lump sum | 5,00,000 |
| 1(g) | Furniture Work (60% of Total BUA) | 631.656 Sqm @ ₹7,500/Sqm | 47,37,420 |
| Sub-Total (Essential Items 1a-1g) | 3,82,88,841 | ||
| 2 | Water Supply & Sanitary Works | 5% of Building Proper | 16,61,466 |
| 3(i) | Electrification — Internal | 5% of Building Proper | 16,61,466 |
| 3(ii) | Electrification — External | 6% of Building Proper | 19,93,759 |
| 3(iii) | Fire Fighting Arrangements | Lump sum | 10,00,000 |
| Sub-Total (Water & Sanitary + Electrification) | 63,16,691 | ||
| Sub-Total (Section A — Essential) | 4,82,04,532 |
Miscellaneous Items (Section B):
| Sr. No. | Item | Specification | Cost (₹) |
|---|---|---|---|
| (i) | Compound Wall & Gate | 300 metre @ ₹10,000/metre | 30,00,000 |
| (ii) | Internal Road | 200 metre × 5 metre = 1,000 Sqm @ ₹3,000/Sqm | 30,00,000 |
| (iii) | Development of Ground | Lump sum | 10,00,000 |
| (iv) | Parking | Lump sum | 20,00,000 |
| (v) | Retaining Wall/Protection Wall | 50 Rmt @ ₹15,000/Rmt | 0 |
| (vi) | Landscaping | Lump sum | 10,00,000 |
| (vii) | Soil Investigation & Detail Land Survey | Lump sum | 3,00,000 |
| (viii) | CC Drain and CD Works | Lump sum | 0 |
| Sub-Total (Section B — Miscellaneous) | 1,03,00,000 |
Optional Items (Section C) — not included in base sanction:
| Sr. No. | Item | Specification | Cost (₹) |
|---|---|---|---|
| 1 | Underground Water Tank for RM/Harvesting | (Cu.M.) Lump sum | 10,00,000 |
| 2 | Water Main Storage & Pump House Borewell | Lump sum | 15,00,000 |
| 3 | Air Conditioning | Lump sum | 10,00,000 |
| 4 | Lifts | Lump sum | 0 |
| 5 | External Toilet | Lump sum | 10,00,000 |
| 6 | AB Room, Area Lighting, Pumps, Generator | Lump sum | 20,00,000 |
Provisions (Section D):