अधीक्षक, राज्य उत्पादन शुल्क, जालना यांचे कार्यालयाच्या प्रशासकीय इमारतीच्या बांधकामास प्रशासकीय मान्यता प्रदान करणेबाबत.

Reference
202102181751481829
Issued
15 Feb 2021
Source
GR Portal (Home Dept - State Excise)
Category
Gr Home Dept

What This Document Says

MAHARASHTRA EXCISE DEPARTMENT — DOCUMENT ANALYSIS

Document Type: Government Resolution (GR) — Administrative Sanction for Capital Works

Reference Number: GR No. BGT-1021/Pr.Cr.43/RAUSHU-1

Issued By: Government of Maharashtra, Home Department (गृह विभाग)

Effective Date: 15 February 2021

Portal ID: 1498


SUMMARY

This Government Resolution grants administrative sanction for the construction of an administrative office building for the Superintendent of State Excise, Jalna (अधीक्षक, राज्य उत्पादन शुल्क, जालना). The total approved cost is ₹8,62,96,191 (Eight Crore, Sixty-Two Lakh, Ninety-Six Thousand, One Hundred and Ninety-One only) based on 2019-20 budget provisions. The sanction is issued under the control of the Principal Secretary, State Excise, and the funds will be drawn from the Major Head "4059 — Public Works Overhead Capital (15) Prohibition and State Excise, (15)(01) Major Works (Scheme) (4059-1033-53 Major Works."


KEY PROVISIONS

Administrative Approval:

  • Administrative sanction granted for construction of office building at Survey No. 488, Jalna
  • Total approved expenditure: ₹8,62,96,191 (as detailed in the accompanying estimate sheet)
  • Budget year of allocation: 2019-20
  • Sanctioning authority: Government of Maharashtra, Home Department

Funding Source:

  • Major Head: 4059 — Public Works Overhead Capital
  • Sub-head: (15) Prohibition and State Excise
  • Further sub-head: (15)(01) Major Works (Scheme) (4059-1033-53 Major Works)
  • Finance Department approval reference: No. 92/2021/Vyay-8, dated 15.02.2021

Building Specifications (from Estimate Sheet):

  • Built-Up Area (BUA): 1,052.76 sq.m. (comprising Basement + Ground Floor + 1st Floor)
  • Survey No.: 488, Jalna

Project Components (Essential Items):

Sr. No. Component Specification Cost (₹)
1(a) Building Proper (Built-Up Area) Basement + GF + 1st Floor = 1,052.76 Sqm 3,32,29,317
1(b) Fuel Gas Pipeline Lump sum 0
1(c) Bio Digester Lump sum 0
1(d) Rain/Roof Water Harvesting 526.38 Sqm @ ₹800/Sqm 4,21,104
1(e) Solar Rooftop (MoU to be executed) Lump sum 30,00,000
1(f) Ramp for Handicaps Lump sum 5,00,000
1(g) Furniture Work (60% of Total BUA) 631.656 Sqm @ ₹7,500/Sqm 47,37,420
Sub-Total (Essential Items 1a-1g) 3,82,88,841
2 Water Supply & Sanitary Works 5% of Building Proper 16,61,466
3(i) Electrification — Internal 5% of Building Proper 16,61,466
3(ii) Electrification — External 6% of Building Proper 19,93,759
3(iii) Fire Fighting Arrangements Lump sum 10,00,000
Sub-Total (Water & Sanitary + Electrification) 63,16,691
Sub-Total (Section A — Essential) 4,82,04,532

Miscellaneous Items (Section B):

Sr. No. Item Specification Cost (₹)
(i) Compound Wall & Gate 300 metre @ ₹10,000/metre 30,00,000
(ii) Internal Road 200 metre × 5 metre = 1,000 Sqm @ ₹3,000/Sqm 30,00,000
(iii) Development of Ground Lump sum 10,00,000
(iv) Parking Lump sum 20,00,000
(v) Retaining Wall/Protection Wall 50 Rmt @ ₹15,000/Rmt 0
(vi) Landscaping Lump sum 10,00,000
(vii) Soil Investigation & Detail Land Survey Lump sum 3,00,000
(viii) CC Drain and CD Works Lump sum 0
Sub-Total (Section B — Miscellaneous) 1,03,00,000

Optional Items (Section C) — not included in base sanction:

Sr. No. Item Specification Cost (₹)
1 Underground Water Tank for RM/Harvesting (Cu.M.) Lump sum 10,00,000
2 Water Main Storage & Pump House Borewell Lump sum 15,00,000
3 Air Conditioning Lump sum 10,00,000
4 Lifts Lump sum 0
5 External Toilet Lump sum 10,00,000
6 AB Room, Area Lighting, Pumps, Generator Lump sum 20,00,000

Provisions (Section D):

Sr. No. Item Amount (₹)
(i) Contingency 5% of Project Cost 14,29,252
(ii) Supervision Charges 2% of Project Cost 5,71,701
(iii) GST 5% of Project Cost 14,29,252
(iv) Principal's Administrative charges 2% 5,71,701
Sub-Total (Section D — Provisions) 40,01,906

PROJECT COST SUMMARY:

Component Cost (₹)
Section A (Essential Items) 4,82,04,532
Section B (Miscellaneous Items) 1,03,00,000
Sub-Total (A + B) 5,85,04,532
Section D (Provisions: Contingency, Supervision, GST, P.A. Charges) 40,01,906
TOTAL PROJECT COST 6,25,06,438

Note: The document indicates further administrative approvals and expenditure bringing the total to ₹8,62,96,191. This discrepancy suggests the estimate sheet provided is a component cost summary, and additional items (possibly Optional Items from Section C and other charges) are included in the final GR sanction amount.

Unit Cost Analysis (provided in estimate):

  • Building Proper Cost: ₹3,15,779/Sqm
  • Electrical Work: ₹16,122/Sqm
  • Water Supply: ₹1,5,790/Sqm
  • Combined (i+ii+iii): ₹32,7,691/Sqm
  • Total Project Cost Per Sqm: ₹81,971/Sqm

DOCUMENTS/ENCLOSURES REFERENCED

  1. Letter from Joint Commissioner (Administration), State Excise, Mumbai — Reference No. BLD-112020/12428/SAHA, dated 25.01.2021
  2. Letter from Chief Engineer, State PWD, Aurangabad — Reference No. MuAu/2021/Ka.12/Ima/122, dated 12.01.2021
  3. Finance Department GR Corrigendum — Reference No. ArthSan-2020/Pr.Cr.65/Arth-3, dated 1.12.2020
  4. Estimate Sheet / Recapitulation Sheet (attached as detailed cost breakdown)
  5. Technical Approval (from Public Works Division engineers)

WHO IS AFFECTED

  • Superintendent of State Excise, Jalna — primary beneficiary (office building)
  • Public Works Department (PWD), Aurangabad Region — executing agency
  • Executive Engineer, PWD, Jalna — implementation responsibility
  • Commissioner of State Excise, Maharashtra — administrative oversight
  • State Finance Department — budget authority
  • Aurangabad Regional Office, PWD — technical supervision

DISTRIBUTION / COMPLIANCE REQUIREMENTS

This GR has been issued to:

  1. Private Secretary to Minister of State Excise, Ministry, Mumbai
  2. Private Secretary to Deputy Minister, State Excise, Ministry, Mumbai
  3. Principal Secretary, State Excise (for senior-level assistance)
  4. Accountant General, Maharashtra 1 (Audit/Accounts & Legality), Mumbai
  5. Accountant General, Maharashtra 2 (Audit/Accounts & Legality), Nagpur
  6. Commissioner, State Excise, Maharashtra State, Mumbai
  7. Public Works Department, Buildings-2/Accounts-2, Ministry, Mumbai
  8. Chief Engineer, Public Works Department, Aurangabad
  9. Executive Engineer, Public Works Department, Jalna
  10. Office of Home Department/Accounts-2, Ministry, Mumbai
  11. Chief Secretary's Office — State Excise (RAUSHU-1)

IMPORTANT NOTES / CONDITIONS

Authority & Validity:

  • Resolution issued under orders and on behalf of the Governor of Maharashtra
  • Digitally signed by Shashank R. Savant, Desk Officer, Government of Maharashtra
  • Digital Reference Code: 202102181751481829
  • Document available at: www.maharashtra.gov.in

Financial Authorization:

  • Approval from Finance Department (Reference No. 92/2021/Vyay-8, dated 15.02.2021) is mandatory compliance requirement
  • Funds must be drawn only from the specified Major Head and sub-heads
  • No cost overrun is authorized beyond ₹8,62,96,191 without fresh administrative sanction

Project Implementation Conditions (from estimate sheet):

  • Borewell & Water Supply: Government responsibility; conditions relating to borewell and water supply will be borne by Government
  • MoU for Solar Rooftop: Solar rooftop installation (₹30,00,000) contingent on execution of Memorandum of Understanding
  • PWD Responsibility: All future expenditure incurred on installation by department/PWD beyond scope of estimate sheet will be borne by Government/PWD

Technical Approvals:

  • All engineering designs and specifications technically approved by:
    • Chief Engineer, PWD Region, Aurangabad
    • Sub-Divisional Engineer, PWD Sub-Division (North), Jalna

No Additional Financial Liability:

  • Government of Maharashtra assumes no additional financial obligation beyond the sanctioned amount of ₹8,62,96,191

LEGAL REFERENCES

  • Budget Head: 4059 — Public Works Overhead Capital (Major Works under State Excise)
  • Finance Department Sanction: BGT-1021/Pr.Cr.43/RAUSHU-1 framework
  • Public Works Rules (implied compliance with PWD norms and regulations)

NOTES ON DOCUMENT CONDITION

The document provided contains:

  • Page 1: Formal GR notification (in Marathi) with all statutory details
  • Page 2: Distribution list and file references
  • Estimate Sheet: Detailed cost breakdown, unit rates, and technical specifications (partially legible due to image quality; certain sections show OCR artifacts)

The core sanction amount ₹8,62,96,191 is explicitly stated in the Marathi GR text. The estimate sheet provided represents the detailed itemization of project costs, with optional items and provisions accounting for the difference from lower component subtotals shown in the estimate.

मराठीत सारांश

**थोडक्यात:**
जालना जिल्ह्यातील उत्पादन शुल्क विभागाच्या अधीक्षकांच्या कार्यालयासाठी नई प्रशासकीय इमारत बांधण्याला सरकारचे मंजूरी मिळाली आहे.

---

**काय बदलले?**

• जालना शहरात उत्पादन शुल्क विभागाला नई इमारत बांधण्याचा अधिकार मिळाला

• ही इमारत अधीक्षक आणि उत्पादन शुल्क विभागाच्या कर्मचाऱ्यांसाठी आहे

• वर्तमान कार्यालय संभवतः जर्जर आहे किंवा जागा कमी आहे, म्हणून नई इमारत बांधण्याचा निर्णय घेण्यात आला

---

**कोणाला फायदा होणार?**

✓ उत्पादन शुल्क विभागाचे कर्मचारी

✓ दारूबंदी कायदा संबंधी काम पहाणारे नागरिक (बेहतर सेवा)

✓ जालना जिल्हा

---

**महत्त्व:**
हा निर्णय बिनसंदर्भ नव्हे — उत्पादन शुल्क विभागाला योग्य बांधकाम वातावरण मिळणे गरजेचे आहे ताकि दारू नियंत्रण आणि excise duty संकलन सुचारुपणे होऊ शकेल.

Original Document

Disclaimer: This page presents a research-grade plain-language summary of a Government of Maharashtra notification, generated by MyExcise's AI from the original government source. It is not a substitute for the original document or legal advice. Always verify the original PDF (linked above) before acting. MyExcise is a research and reference tool, not a law firm.