Document Type: Government Resolution (Administrative Sanction)
Reference Number: GR No. BBT-1021/Pr.Cr.19/RAUSHU-1
Issued By: Government of Maharashtra, Home Department (माहाराष्ट्र शासन, गृह निभाग)
Date of Issue: 15 February 2021
Digital Portal ID: 202102181803452129 (www.maharashtra.gov.in)
Effective Date: 15 February 2021
This Government Resolution grants administrative sanction for the construction of an office building and residential quarters for the Inspector, State Excise Department, Satana (under the jurisdiction of the Superintendent, State Excise, Nashik). The project cost of ₹9,60,38,000/- (Nine Crore Sixty Lakh Thirty-Eight Thousand rupees only) is approved for expenditure from the Public Works Budget head "4059 — Public Works Capital Expenditure, (15) Excise and State Excise, (15)(01) Major Works (Programme) (4059 1033) — 53 Major Works". The sanction is issued following financial clearance from the Finance Department and in compliance with the prescribed administrative procedures.
• Project: Construction of office building and residential quarters for Inspector, State Excise, Satana, District Nashik.
• Location: Plot No. 1064, Site No. 215, under the jurisdiction of Superintendent, State Excise, Nashik.
• Total Sanctioned Cost: ₹9,60,38,000/- (Nine Crore Sixty Lakh Thirty-Eight Thousand rupees only) — as detailed in the accompanying Bill of Quantities / Recapitulation Sheet.
• Budget Head: 4059 — Public Works Capital Expenditure
• Financial Sanction Reference: Finance Department Corrigendum No. 92/2021/Vyay-8, dated 15 February 2021.
• Sanctioning Authority: Government of Maharashtra, Home Department, acting under the orders of the Governor of Maharashtra.
• Approval Status: Project approved for implementation by the competent authority.
| Floor | Built-Up Area (Sqmt) | Unit Rate (₹/Sqmt) | Total Cost (₹) |
|---|---|---|---|
| Ground Floor (including Plinth Protection) | 217.64 | 30,030.00 | 6,535,729.00 |
| First Floor | 560.44 | 27,060.00 | 15,165,506.00 |
| Second Floor | 652.54 | 28,160.00 | 18,375,526.00 |
| TOTAL — Main Building | 1,430.62 | — | 40,076,761.00 |
| Floor | Built-Up Area (Sqmt) | Unit Rate (₹/Sqmt) | Total Cost (₹) |
|---|---|---|---|
| Stilt Floor | 140.03 | 14,245.00 | 1,994,656.00 |
| First Floor | 140.03 | 26,730.00 | 3,742,868.00 |
| TOTAL — Residential Quarters | 280.05 | — | 5,737,524.00 |
| Component | Amount (₹) |
|---|---|
| Fuel Gas Line | [Amount shown as struck/edited in original document] |
| Biodigester | [Amount shown as struck/edited in original document] |
| Rain / Roof Water Harvesting & Stormwater Drainage | [Amount shown as struck/edited in original document] |
| Solar Roof Top (MoU to be executed) | [Amount shown as struck/edited in original document] |
| Ramp for Handicaps | 50,000.00 |
| Furniture | 6,064,900.00 (1,212.98 units @ ₹5,000/Sqmt) |
| Project Management Consultancy Charges (including Architect/Consultancy/Design) | 0.00% of (a) = 0.00 |
| Sub-Total (b+c+d+e+f+g+h) | ₹7,031,186.00 |