Document Type: Government Resolution (GR) — Administrative Sanction for Capital Works
Reference Number: GR No. BGT-1020/PR.CR.24/RAUSHU-1, Dated 15 February 2021
Issued By: Government of Maharashtra, Home Department (गृह विभाग)
Effective Date: 15 February 2021 (Date of Government Resolution)
Summary: This GR grants administrative sanction for the construction of an office building for the Superintendent, State Excise Department, Amravati. The total sanctioned expenditure is ₹6,61,46,000/- (Six Crores Sixty-One Lakh Forty-Six Thousand only). The project covers Site No. 48, Plot No. 19, and includes construction of a new office building with essential facilities, miscellaneous items, and infrastructure. Funding will be met from the budget head "4059 — Capital Expenditure on Public Works, (15) Excise and State Production Tax, (15)(01) Major Works (Scheme) (4059 1033)-53 Major Works" with Finance Department approval reference No. 92/2021/EXP-8, dated 15.02.2021.
• Sanctioned Work: Construction of office building for Superintendent, State Excise Department, Amravati at Site No. 48, Plot No. 19 • Total Sanctioned Cost: ₹6,61,46,000/- (Six Crores Sixty-One Lakh Forty-Six Thousand only) • Funding Head: Budget Head 4059 — Capital Expenditure on Public Works, (15) Excise and State Production Tax, (15)(01) Major Works (Scheme) (4059 1033)-53 Major Works • Finance Approval: Approved by Finance Department with Reference No. 92/2021/EXP-8, dated 15.02.2021 • Project Components: As detailed in the attached cost estimate (Recapitulation Sheet) • Execution Authority: Public Works Department (सावणजनिक बांधकाम विभाग), Amravati • Responsible Officer: Chief Engineer, Public Works Department, Amravati
| Component Category | Unit | Rate (₹) | Quantity | Total Cost (₹) |
|---|---|---|---|---|
| ESSENTIAL ITEMS (A) | ||||
| Building Proper — Ground Floor | Sqm | 11,454.00 | 613.90 | 7,031,869.60 |
| Building Proper — First Floor | Sqm | 20,412.00 | 609.89 | 12,455,235.00 |
| Building Proper Subtotal | 29,868,226.00 | |||
| Fuel Gas Pipeline | L.S | — | — | 300,000.00 |
| Bio Digester | L.S | — | — | 300,000.00 |
| Rain/Roof Water Harvesting | L.S | — | — | 1,500,000.00 |
| Solar Roof Top Power Saving Installations (MoU to be executed) | L.S | — | — | 1,500,000.00 |
| Ramp for Handicaps | L.S | — | — | 200,000.00 |
| Furniture (₹5,000 per Sqm — 30% Floor Area) | L.S | 5,000.00 | 1,164.10 | 5,820,500.00 |
| Dismantling of Old Building | L.S | — | — | 1,000,000.00 |
| Subtotal (Essential Items B+C+D+E+F+G) | 9,120,500.00 | |||
| Subtotal Essential Items (A) | 44,767,644.00 | |||
| MISCELLANEOUS ITEMS (B) | ||||
| Compound Wall & Gate (Running Meter) | Meter | 210.70 | 10,710.00 | 2,256,597.00 |
| Internal Roads (Running Meter) | Meter | 3,402.00 | 611.00 | 2,078,622.00 |
| Development of Ground | L.S | — | — | 500,000.00 |
| Parking | L.S | — | — | 200,000.00 |
| Retaining Wall | — | — | — | — |
| Land Seeping | — | — | — | — |
| Soil Investigations & Detail Land Survey | — | — | — | — |
| CC Drain | — | 249.99 | — | — |
| Subtotal (B) | 5,035,219.00 | |||
| GRAND TOTAL SANCTIONED COST | ₹6,61,46,000.00 (Approximately) |
| Item | Rate | Basis | Cost (₹) |
|---|---|---|---|
| Water Supply & Sanitary Works | 5% of Building Proper Cost | 5% of ₹29,868,226 | 1,493,412.00 |
| Item | Rate | Basis | Cost (₹) |
|---|---|---|---|
| Internal Electrification | 6% of Building Proper Cost | 6% of ₹29,868,226 | 1,792,094.00 |
| External Electrification | 5% of Building Proper Cost | 5% of ₹29,868,226 | 1,493,412.00 |
| Fire Fighting Arrangements | L.S | — | 1,000,000.00 |
| Subtotal Electrification | 5,778,918.00 |
References/Correspondence Files:
This Government Resolution has been forwarded to:
Building Structure:
Integrated Facilities:
Infrastructure Components:
Service Connections:
• Digital Authentication: This Government Resolution has been issued with digital signatures (डिजिटली स्वाक्षरीने साक्षांकित)
• Portal Publication: The GR is available on the Maharashtra Government website (www.maharashtra.gov.in) with Computer Reference Code: 202102181741369429
• Governor's Authority: This order is issued under and in the name of the Governor of Maharashtra (महाराष्ट्राचे राज्यपाल याांच्या आदेशानुसार व नावाने)
• Signatory Authority: Order signed by Shashanck R. Sawant (शशांक र. सावंत), Chamber Officer, Government of Maharashtra
• Budget Availability: Sanctioned cost will be met from the allocated provisions under Budget Head 4059-53 (Major Works) for the current/subsequent financial year as per budget availability
• Finance Department Concurrence: This GR has been issued with the concurrence and approval of the Finance Department (ववत्त ववभागाच्या सहमतीने वनगणवमत)
• Project Coordination: The Chief Engineer, PWD, and Executive Engineer, PWD, Amravati, shall coordinate with the State Excise Department for timely execution and quality assurance
• MoU Requirement: Solar installations require execution of Memorandum of Understanding (MoU) between State Excise Department and concerned renewable energy authority
| Milestone | Date |
|---|---|
| Joint Commissioner (Administration) Letter | 23.12.2020 |
| Chief Engineer PWD, Regional Reference | 11.10.2019 |
| Finance Department Corrigendum | 1.12.2020 |
| Finance Department Approval Reference | 15.02.2021 |
| Government Resolution Issued | 15.02.2021 |
Not Applicable — This GR pertains to capital infrastructure development and administrative sanction for construction. It does NOT directly affect any specific Excise License Categories (FL-I, FL-II, FL-III, FL-IV, CL-I, CL-II, CL-III, Toddy, Neera, etc.). However, it relates to the office infrastructure of the State Excise Department, Amravati, which is the regulatory body issuing and managing all such licenses.
✅ Valid Government Resolution
✅ Digitally Signed and Authenticated
✅ Published on Official Maharashtra Government Portal
✅ All Financial Approvals Obtained
✅ Effective Immediately from 15.02.2021
End of Analysis