What This Document Says

MAHARASHTRA EXCISE OFFICIAL DOCUMENT ANALYSIS

Document Type: Government Resolution (GR) / Administrative Sanction Order

Reference Number: GR No. BGT-1021/Pr.Kr.39/RAUSHU-1, Dated 17 June 2021

Issued By: Home Department (गृह विभाग), Government of Maharashtra

Effective Date: 17 June 2021

Summary: This Government Resolution grants administrative sanction for the construction of a new office building for the Superintendent, State Excise (राज्य उत्पादन शुल्क), Ahmednagar. The total project cost approved is ₹13,21,86,208/- (Thirteen Crore Twenty-One Lakh Eighty-Six Thousand Two Hundred and Eight rupees only) for construction on Plot No. 193, Ahmednagar. The project is sanctioned under the Financial Authority Rules 1978 Part-I, Sub-section Five, Article 1, and Maharashtra Public Works Rules, Section 134. This is an infrastructure development order affecting the State Excise Department's administrative capacity in the Ahmednagar district.


KEY PROVISIONS:

Administrative Sanction Details:

  • Project Title: Construction of State Excise Office Building (Administrative Building), Ahmednagar
  • Location: Plot No. 193, Ahmednagar Taluka and District Ahmednagar
  • Sanctioning Authority: Home Department, Government of Maharashtra
  • Authority under which sanctioned: Financial Authority Rules 1978, Part-I, Sub-section 5, Article 1 AND Maharashtra Public Works Rules, Section 134
  • Sanction Dated: 17 June 2021
  • Budget Head / Fund Allocation:

    • Budget Head: Demand H-8, Main Account Head 4059 - Public Works Capital Expenditure
    • Sub-head: (15) Prohibition and State Excise
    • Further Sub-head: (15)(01) Major Works (Programme) (4059-1033) - 53 Major Works
    • Fund Source: To be met from allocations under the above budget head
    • Approval Reference: Public Works Department Consent No. AUN SAN-57/2021/IMA-2, Dated 10.05.2021
    • Project Cost Breakdown:

      Cost Component Amount (₹)
      ESSENTIAL ITEMS (A)
      Building Proper (Built-up Area: 3,087.62 Sq.M @ ₹23,000/Sq.M) 71,015,260
      Furniture (1,679 Sq.M @ ₹5,000/Sq.M) 8,393,280
      Rain/Roof Water Harvesting 5,00,000
      Solar Rooftop (MoU to be executed)* 5,00,000
      Ramp for Handicaps 2,00,000
      Water Supply & Sanitary Works (5% of building cost) 35,50,763
      Electrification - Internal (5% of building cost) 35,50,763
      Electrification - External (6% of building cost) 42,60,916
      Fire Fighting Arrangements etc. 50,00,000
      SubTotal (A) Essential Items 96,97,0,982
      MISCELLANEOUS ITEMS (B)
      Compound Wall & Gate (380 Rmt @ ₹5,000/Rmt) 19,00,000
      Internal Roads (700 Rmt @ ₹2,500/Rmt) 17,50,000
      Development of Ground, Horticulture 2,00,000
      Parking 5,00,000
      Landscaping 2,00,000
      Soil Investigations & Detail Land Survey 2,00,000
      CC Drains and CID Works 5,00,000
      Dismantling Old Building 2,00,000
      SubTotal (B) Miscellaneous Items 54,50,000
      OPTIONAL ITEMS (C)
      Underground Water Tank for R/W Harvesting 5,00,000
      Water Main Storage, Pumphouse, Borewell 5,00,000
      Air Conditioning 10,00,000
      External Toilets 2,00,000
      ABRoom, Area Lighting, Pumps, Generator 10,00,000
      CCTV 3,00,000
      Gardening/Plantation of Trees 1,00,000
      SubTotal (C) Optional Items 36,00,000
      SUBTOTAL PROJECT COST (A+B+C) 10,60,20,982
      PROVISIONS (D)
      Contingencies (4% on Essential Items) 28,40,610
      GST (12% on Project Cost) 1,27,22,518
      Price Escalation (10% on Project Cost) 1,06,02,098
      SubTotal (D) Provisions 2,61,65,226
      TOTAL COST OF PROJECT (A+B+C+D) ₹13,21,86,208

      Plinth Area Rates:

      • Building Proper Cost: ₹23,000/Sq.M
      • Electrification Work: ₹4,149/Sq.M
      • Water Supply: ₹1,150/Sq.M
      • Building + Electrification + Water Supply (Combined): ₹28,299/Sq.M
      • Total Project Cost Per Sq.M (including all items): ₹42,812/Sq.M
      • Total Project Cost Per Total Area: ₹1,321.86 Lakhs

      • DOCUMENTS/ENCLOSURES REFERENCED:

मराठी अनुवाद (Marathi Translation)
गृह विभाग), राज्य उत्पादन शुल्क),

Sign in to continue reading

15 days of full content access — every Act, Rule, Regulation, GR, notification and Ex-DC-authored guide. No card required.
पूर्ण मजकूर पाहण्यासाठी साइन इन करा

Sign in with Google Already have an account? Sign in

मराठीत सारांश

**थोडक्यात:**
अहमदनगर येथे Excise Department च्या अधीक्षकांच्या कार्यालयाची इमारत बांधण्याला सरकारी परवानगी दिली गेली आहे.

---

**विस्तारित माहिती:**

**कायदा कोणता?**
महाराष्ट्र दारूबंदी कायदा आणि उत्पादन शुल्क विभागाशी संबंधित.

**या notification मध्ये काय आहे?**
- अहमदनगर जिल्ह्यात Excise Department च्या अधीक्षकांचे नवे कार्यालय बांधण्याचा निर्णय घेण्यात आला
- हे कार्यालय दारूबंदी कायद्याशी संबंधित कामकाज करेल
- इमारतीच्या बांधकामाची अनुमती सरकारने (गृह विभाग) दिली

**कोण लाभवंत होणार?**
- Excise Department ला आधुनिक कार्यालय मिळेल
- अहमदनगर जिल्ह्यातील दारू-संबंधित कामकाज अधिक चांगल्या तरीने होऊ शकेल
- नागरिकांना licence आणि permit मिळवायला सुविधा होईल

**महत्वाचे:**
हा शुद्ध प्रशासकीय निर्णय आहे — सामान्य नागरिकांना कोणतीही नवीन जबाबदारी नाही.

Original Document

Share: WhatsApp
Disclaimer: This page presents a research-grade plain-language summary of a Government of Maharashtra notification, generated by MyExcise's AI from the original government source. It is not a substitute for the original document or legal advice. Always verify the original PDF (linked above) before acting. MyExcise is a research and reference tool, not a law firm.
Link copied to clipboard!
Ask MyExcise AI MyExcise AI