Document Type: Government Resolution (GR) / Administrative Sanction Order
Reference Number: GR No. BGT-1021/Pr.Kr.39/RAUSHU-1, Dated 17 June 2021
Issued By: Home Department (गृह विभाग), Government of Maharashtra
Effective Date: 17 June 2021
Summary: This Government Resolution grants administrative sanction for the construction of a new office building for the Superintendent, State Excise (राज्य उत्पादन शुल्क), Ahmednagar. The total project cost approved is ₹13,21,86,208/- (Thirteen Crore Twenty-One Lakh Eighty-Six Thousand Two Hundred and Eight rupees only) for construction on Plot No. 193, Ahmednagar. The project is sanctioned under the Financial Authority Rules 1978 Part-I, Sub-section Five, Article 1, and Maharashtra Public Works Rules, Section 134. This is an infrastructure development order affecting the State Excise Department's administrative capacity in the Ahmednagar district.
| Cost Component | Amount (₹) |
|---|---|
| ESSENTIAL ITEMS (A) | |
| Building Proper (Built-up Area: 3,087.62 Sq.M @ ₹23,000/Sq.M) | 71,015,260 |
| Furniture (1,679 Sq.M @ ₹5,000/Sq.M) | 8,393,280 |
| Rain/Roof Water Harvesting | 5,00,000 |
| Solar Rooftop (MoU to be executed)* | 5,00,000 |
| Ramp for Handicaps | 2,00,000 |
| Water Supply & Sanitary Works (5% of building cost) | 35,50,763 |
| Electrification - Internal (5% of building cost) | 35,50,763 |
| Electrification - External (6% of building cost) | 42,60,916 |
| Fire Fighting Arrangements etc. | 50,00,000 |
| SubTotal (A) Essential Items | 96,97,0,982 |
| MISCELLANEOUS ITEMS (B) | |
| Compound Wall & Gate (380 Rmt @ ₹5,000/Rmt) | 19,00,000 |
| Internal Roads (700 Rmt @ ₹2,500/Rmt) | 17,50,000 |
| Development of Ground, Horticulture | 2,00,000 |
| Parking | 5,00,000 |
| Landscaping | 2,00,000 |
| Soil Investigations & Detail Land Survey | 2,00,000 |
| CC Drains and CID Works | 5,00,000 |
| Dismantling Old Building | 2,00,000 |
| SubTotal (B) Miscellaneous Items | 54,50,000 |
| OPTIONAL ITEMS (C) | |
| Underground Water Tank for R/W Harvesting | 5,00,000 |
| Water Main Storage, Pumphouse, Borewell | 5,00,000 |
| Air Conditioning | 10,00,000 |
| External Toilets | 2,00,000 |
| ABRoom, Area Lighting, Pumps, Generator | 10,00,000 |
| CCTV | 3,00,000 |
| Gardening/Plantation of Trees | 1,00,000 |
| SubTotal (C) Optional Items | 36,00,000 |
| SUBTOTAL PROJECT COST (A+B+C) | 10,60,20,982 |
| PROVISIONS (D) | |
| Contingencies (4% on Essential Items) | 28,40,610 |
| GST (12% on Project Cost) | 1,27,22,518 |
| Price Escalation (10% on Project Cost) | 1,06,02,098 |
| SubTotal (D) Provisions | 2,61,65,226 |
| TOTAL COST OF PROJECT (A+B+C+D) | ₹13,21,86,208 |