This Government Resolution grants administrative approval and financial sanction for the construction of an administrative building for the State Excise Department at Bhandar taluka, Bhandar district, Maharashtra. The project is sanctioned at a total cost of ₹8,46,82,000 (Eight crores forty-six lakhs eighty-two thousand rupees). The work is to be constructed on Nazul Sheet No. 35, Plot No. 4 (area 3,624 sq.mt.) and consists of a G+2 (Ground + 2 floors) administrative building. The project includes all associated civil, electrical, water supply, sanitary, and miscellaneous works as detailed in the attached recapitulation sheet. Funding is authorized from the current financial year 2021-22 budget under the Major Works programme (head 4059-1033).
1. ESSENTIAL ITEMS:
| Component | Area/Quantity | Unit Rate | Total Cost (₹) |
|---|---|---|---|
| (a) Building Proper (Built-up Area) | |||
| Basement | 0.00 | Sq.mt | 0.00 |
| Stilt Floor | 0.00 | Sq.mt | 0.00 |
| Ground Floor (Administrative Building G+2) | 348.24 Sq.mt | ₹35,048 Per Sq.mt | 12,205,221.00 |
| 1st Floor | 407.93 Sq.mt | ₹28,080 Per Sq.mt | 11,454,618.00 |
| 2nd Floor | 407.93 Sq.mt | ₹29,484 Per Sq.mt | 12,027,349.00 |
| Foundation in B.C./Weak Soil | 0.00 | Sq.mt | 0.00 |
| Total Built-up Area: | 1,164.10 Sq.mt | 35,687,188.00 | |
| (b) Rain/Roof Water Harvesting | Lump Sum | 500,000.00 | |
| (c) Ramp for Handicaps | Lump Sum | 500,000.00 | |
| (d) Office Furniture | Lump Sum | 1,500,000.00 | |
| Sub-Total (Essential Items): | 42,507,683.00 |
2. WATER SUPPLY AND SANITARY WORKS:
| Item | Quantity | Unit Rate | Total Cost (₹) |
|---|---|---|---|
| Internal (5% of Building Cost) | 1,784,359.00 | ||
| External (6% of Building Cost) | 2,141,231.00 | ||
| Sub-Total (Water Supply & Sanitary Works): | 3,925,590.00 |
3. ELECTRICAL WORKS:
| Item | Specification | Total Cost (₹) |
|---|---|---|
| (a) External Electrification | 6% of Building Cost | 2,550,461.00 |
| (b) Other Electrical Items: | ||
| Generator | 5 KVA Capacity | 1,000,000.00 |
| Fire Fighting Arrangement | Lump Sum | 1,200,000.00 |
| Supply Charges | Lump Sum | 1,200,000.00 |
| External Arc Lighting | 10 KX System | 540,000.00 |
| Renewable Energy/Solar Energy System | Lump Sum | 200,000.00 |
| Air Conditioning/Central Cooling | Sub-Station etc. | 500,000.00 |
| Transformer/Electric Sub-Station | Lump Sum | 2,000,000.00 |
| CCTV (Special Item) | Lump Sum | 2,800,100.00 |
| Sub-Total (Other Electrical Items): | 9,440,100.00 | |
| Sub-Total (Electrical Works 3a + 3b): | 11,990,561.00 |
4. MISCELLANEOUS ITEMS: