Document Type: Government Resolution (GR) — Capital Works Sanction
Reference Number: GR No. BGT-1008/Pr.Cr.58/ESC-4, dated 19 October 2018
Issued By: Maharashtra Government, Home Department (गृह विभाग)
Effective Date: 19 October 2018
This Government Resolution grants revised administrative approval for the construction of office buildings for the Divisional Deputy Commissioner & Superintendent, State Excise Department, Nagpur, and subordinate offices under both these offices, to be constructed at the Cotton Market Warehouse premises, Nagpur. The original sanctioned cost of ₹6,35,23,682 is being revised downward to ₹6,09,90,777 based on revised estimates due to ongoing architectural and electrification works. The funds will be released from the Main Accounts head "4059 — Contingent Expenditure on Public Works, (15) Prohibition and State Excise, (15) (01) Major Works (Programme) (4059 1033) — Major Works."
• Project Location: Cotton Market Warehouse, Nagpur — premises of the State Excise Department
• Beneficiary Office:
• Purpose: Construction of office building for the above two offices
• Original Administrative Sanction: ₹6,35,23,682 (Six Crore Thirty-Five Lakh Twenty-Three Thousand Six Hundred Eighty-Two rupees only) vide GR dated 70.70.2010 (Home Department, GR No. BGT-1008/Pr.Cr.58/ESC-4)
• Revised Administrative Sanction: ₹6,09,90,777 (Six Crore Nine Lakh Ninety Thousand Seven Hundred Seventy-Seven rupees only)
• Expenditure Incurred to Date: ₹5,78,80,777 as on the date of this GR
• Additional Funds Required (as per Deputy Commissioner's letter dated 25.70.2708):
• Total Expected Final Cost: ₹6,09,90,777
• Reduction from Original Sanction: ₹25,32,905 (₹6,35,23,682 − ₹6,09,90,777)
• Secretary Committee Approval: The proposal was placed before the Secretary Committee under the chairmanship of the Principal Secretary (Home) on 2370.2704 (date referenced as per Marathi calendar). The Committee initially approved an estimated value of ₹595.52 lakh for the work.
• Source of Funds: The expenditure shall be met from the sanctioned budget allocation under:
• Public Works Department Approval: This GR is issued with the approval of the Public Works Department (Department of Public Works) vide their Reference No. 437/08/Ima-2, dated 79.07.2708
• Cross-References:
• Portal Publication: The GR has been published on the Government of Maharashtra official website (www.maharashtra.gov.in) with portal reference number 201810191444473129
• Digital Signature: The order is authenticated with a digital signature as per Government of Maharashtra standards
• Signatory Authority:
Cost Revision Rationale: The cost has been revised downward by ₹25,32,905 from the originally sanctioned amount. This reflects either:
Pending Works (as of GR date):
No Excise License Impact: This GR pertains exclusively to capital works/infrastructure development and does NOT affect:
Budgetary Allocation Approved: The expenditure is authorized to be drawn from the Main Accounts classification, ensuring proper budgetary control and audit trail
Inter-Departmental Coordination: The GR demonstrates approval from multiple government departments:
No Appeals Process Mentioned: As this is an infrastructure GR (not a licensing or penalty matter), standard administrative appeal procedures under relevant administrative codes would apply if any party wishes to challenge administrative decisions.
Direct Beneficiary:
Implementing Agencies:
Financial Oversight:
Non-Affected Parties:
| Date Reference | Interpretation | Actual Date (if decipherable) |
|---|---|---|
| 70.70.2010 | Original GR date | 70th day, 70th month(?), 2010 — FORMAT UNCLEAR |
| 37.0.2702 | Planning Dept. Circular date | 37th day(?), 0th month(?), 2702 — FORMAT UNCLEAR |
| 2370.2704 | Secretary Committee Meeting | 2370th day(?), 2704 — FORMAT UNCLEAR |
| 25.70.2708 | Deputy Commissioner's letter | 25th day, 70th month(?), 2708 — FORMAT UNCLEAR |
| 19 October 2018 | GR Issuance Date | 19 October 2018 ✓ |
| 79.07.2708 | PWD Approval date | 79th day, 07th month(?), 2708 — FORMAT UNCLEAR |
Note: Multiple dates in the document appear corrupted or use non-standard date formatting (possibly OCR errors or archival notation). The only clearly legible date is 19 October 2018, which is the GR publication date.
| Item | Amount (₹) | Status |
|---|---|---|
| Original Sanctioned Cost | 6,35,23,682 | Per GR dated 70.70.2010 |
| Expenditure to Date | 5,78,80,777 | Actual spend as of GR date |
| Pending Architectural Works | 82,77,000 | Additional requirement |
| Pending Electrification Works | 29,74,000 | Additional requirement |
| Total Additional Required | 1,12,51,000 | Total shortfall |
| Revised Total Sanction | 6,09,90,777 | Current GR Approval |
| Cost Reduction | (25,32,905) | Downward revision |