Document Type: Government Resolution (GR) — Administrative Sanction for Building Construction
Reference Number: GR No. BGT-1024/Pr.Cr.27/RAU-1, dated 04 July 2024
Issued By: Government of Maharashtra, Home Department (गृह निभाग), Mantralaya, Mumbai-400 032
Effective Date: 04 July 2024
Summary: This GR grants administrative sanction for construction of a new administrative building for the Inspector of State Excise, Gondia office. The existing administrative building at Jaystambh Chowk, Gondia (Plot No. 7, Municipal Sheet No. 31) has become unfit for use. The sanction approves expenditure of ₹3,35,87,181 (Three crore thirty-five lakh eighty-seven thousand one hundred eighty-one rupees only) for the new building construction. The project cost includes essential building components, electrical works, civil miscellaneous items, optional items, contingencies, green building concepts, price escalation, GST, architectural services, and labour insurance.
Administrative Authority & References:
Location & Property Details:
Sanction Details:
Budget Head & Fund Allocation:
RECAPITULATION SHEET — DETAILED COMPONENT-WISE COST ANALYSIS
| Sr.No | Particulars of Scope | Unit Rate Norms (Rs Per) | Component-wise Total (₹) |
|---|---|---|---|
| SECTION (A): ESSENTIAL ITEMS (COMPONENTS) | |||
| 1(a) | Building Proper (Built-Up Area — Sq.m) | ||
| Basement | 00 per sqmt | 00 | |
| Stilt Floor | 00 per sqmt | 00 | |
| Ground Floor of Taluka Level Excise Duty Office | 500.60 per sqmt | 15,018,000 | |
| Sub-total (a) | 15,018,000 | ||
| 1(b) | Fuel Gas Pipeline | Lump sum | 00 |
| 1(c) | Biodigester | Lump sum | 00 |
| 1(d) | Roof / Rain Water Harvesting | Lump sum | 00 |
| 1(e) | Solar Roof Top | Lump sum | 00 |
| 1(f) | Ramp for Handicapped | Lump sum | 00 |
| 1(g) | Furniture | Lump sum | 2,000,000 |
| Sub-total (a+b+c+d+e+f+g) | 17,018,000 | ||
| 2 | Water Supply & Sanitary Work | 5% on total of (a) | 750,900 |
| Sub-total (2) | 750,900 | ||
| 3(a) | Electrification | ||
| Internal | 5% of (a) | 750,900 | |
| External | 6% of (a) | 901,080 | |
| Fire Fighting Arrangement | Lump sum | 500,000 | |
| Sub-total (3a) | 2,151,980 | ||
| SECTION (B): OTHER ELECTRICAL ITEMS | |||
| (i) | Generator 62.5 KVA capacity | Lump sum | 00 |
| (ii) | Supply Charges of MSEDCL (MSEB) | Lump sum | 00 |
| (iii) | External Area Lighting | Lump sum | 00 |
| (iv) | Solar Energy System / Renewal | Lump sum | 00 |
| (v) | Lifts | Lump sum | 00 |
| (vi) | Air Conditioning / Central Cooling | Lump sum | 00 |
| (vii) | Transformer / Electric Sub-station etc. | Lump sum | 00 |
| (viii) | CCTV | Lump sum | 00 |
| (ix) | Any Other Electrical Item (Please Specify) | Lump sum | 00 |
| Sub-total (B) | 00 | ||
| Total Electrical Sub-Total (3) = (3a)+(3b) | 2,151,980 | ||
| Sub-Total (A) = 1+2+3 | 19,920,880 | ||
| SECTION (B): MISCELLANEOUS CIVIL ITEMS | |||
| (i) | Compound Wall & Gate (Rmt) | Per Rmt | 2,500,000 |
| (ii) | Internal Road Pathway etc. | Sqmt | 00 |
| (iii) | Dismantling Existing Building | Per Km | 1,500,000 |
| (iv) | Parking | Per Rmt | 00 |
| (v) | Retaining Wall | Per Sqm | 00 |
| (vi) | Land Scraping / Gardening | Lump sum | 00 |
| (vii) | Soil Investigation & Detailed Land Survey | Lump sum | 00 |
| (viii) | C.C. Drain At Road Side & for Sanitary Disposal | Per Km | 00 |
| Sub-total (B) | 4,000,000 | ||
| SECTION (C): OPTIONAL ITEMS | |||
| 1 | Underground Water Tank for Rain Water Harvesting | Lump sum | 00 |
| 2 | Water Main Storage Pump House 2 Bore Well | Lump sum | 500,000 |
| 3 | Air Conditioning | Lump sum | 00 |
| 4 | Lift Installation | Lump sum | 00 |
| 5 | External Toilets | Lump sum | 00 |
| 6 | AB Room, Area Lightening, Pumps, Generators | Lump sum | 00 |
| 7 | CCTV | Lump sum | 00 |
| Sub-total (C) | 500,000 | ||
| PROJECT COST (P) = (A+B+C) | 24,420,880 | ||
| SECTION (D): OTHER PROVISIONS | |||
| i | Contingencies | 4% on (P) | 600,720 |
| ii | Green Building Concept | 5% on total civil cost | 750,300 |
| iii | Price Escalation | 10% on (P) | 2,442,088 |
| iv | GST (Goods & Services Tax) | 18% on total of (P) | 4,395,758 |
| v | Architectural Services | 3 to 5% on (P) | 732,626 |
| vi | Labour Insurance | 17% on (P) | 244,205 |
| Sub-total (D) | 9,166,301 | ||
| TOTAL COST OF PROJECT (TPC) = A+B+C+D | ₹33,587,181 | ||
| SAY IN LAKH | 335.87 Lakh |
Attached Documentation:
Reference Documents Cited (Not Directly Attached but Form Basis):
Direct Beneficiary:
Administrative/Implementation Authorities: