What This Document Says

MAHARASHTRA EXCISE OFFICIAL DOCUMENT ANALYSIS

Document Type: Government Resolution (GR) — Administrative Sanction for Building Construction

Reference Number: GR No. BGT-1024/Pr.Cr.27/RAU-1, dated 04 July 2024

Issued By: Government of Maharashtra, Home Department (गृह निभाग), Mantralaya, Mumbai-400 032

Effective Date: 04 July 2024

Summary: This GR grants administrative sanction for construction of a new administrative building for the Inspector of State Excise, Gondia office. The existing administrative building at Jaystambh Chowk, Gondia (Plot No. 7, Municipal Sheet No. 31) has become unfit for use. The sanction approves expenditure of ₹3,35,87,181 (Three crore thirty-five lakh eighty-seven thousand one hundred eighty-one rupees only) for the new building construction. The project cost includes essential building components, electrical works, civil miscellaneous items, optional items, contingencies, green building concepts, price escalation, GST, architectural services, and labour insurance.


KEY PROVISIONS

Administrative Authority & References:

  • Government Resolution, Home Department, Ref. No. BGT-1024/Pr.Cr.27/RAU-1, dated 04.07.2024
  • Issued under powers derived from Financial Authority Handbook 1978, Part-I, Sub-section 5, Item No. 1 and Maharashtra Public Works Rules, Section 134
  • Based on Government Circular, Public Works Department, Ref. No. Sankirna-2019/Pr.Cr.10/Ima-2, dated 25.09.2019
  • Cross-referenced: GR Home Department, Ref. No. BGT-1021/Pr.Cr.259/RAU-1, dated 10.01.2023
  • Cross-referenced: Letter from Joint Commissioner (Administration), State Excise, Mumbai, Ref. No. BLD112021/I.Du/Saha, dated 09.01.2024
  • Location & Property Details:

    • Office: Inspector, State Excise Department, Gondia
    • Location: Jaystambh Chowk, Gondia
    • Property Details: Plot No. 7, Municipal Sheet No. 31, Gondia
    • Existing building status: Declared unfit for continued use
    • Action: New administrative building to be constructed at same location
    • Sanction Details:

      • Total Project Cost (TPC): ₹3,35,87,181 (Rupees Three crore thirty-five lakh eighty-seven thousand one hundred eighty-one only)
      • Sanction granted for construction of new administrative building as per attached cost estimation sheet (Recapitulation Sheet)
      • Budget Head & Fund Allocation:

        • Demand No.: H-8
        • Main Account Head: 4059 — Public Works Capital Expenditure
        • Sub-head: (15) Excise and State Excise Duty
        • Sub-sub-head: (15)(01) Major Works (Programme) (4059 1033) — 53 Major Works
        • Funds to be drawn from available provision under this budget head
        • Expenditure to be booked under the same budget head

        • FEE SCHEDULE / PROJECT COST BREAKDOWN

          RECAPITULATION SHEET — DETAILED COMPONENT-WISE COST ANALYSIS

          Sr.No Particulars of Scope Unit Rate Norms (Rs Per) Component-wise Total (₹)
          SECTION (A): ESSENTIAL ITEMS (COMPONENTS)
          1(a) Building Proper (Built-Up Area — Sq.m)
          Basement 00 per sqmt 00
          Stilt Floor 00 per sqmt 00
          Ground Floor of Taluka Level Excise Duty Office 500.60 per sqmt 15,018,000
          Sub-total (a) 15,018,000
          1(b) Fuel Gas Pipeline Lump sum 00
          1(c) Biodigester Lump sum 00
          1(d) Roof / Rain Water Harvesting Lump sum 00
          1(e) Solar Roof Top Lump sum 00
          1(f) Ramp for Handicapped Lump sum 00
          1(g) Furniture Lump sum 2,000,000
          Sub-total (a+b+c+d+e+f+g) 17,018,000
          2 Water Supply & Sanitary Work 5% on total of (a) 750,900
          Sub-total (2) 750,900
          3(a) Electrification
          Internal 5% of (a) 750,900
          External 6% of (a) 901,080
          Fire Fighting Arrangement Lump sum 500,000
          Sub-total (3a) 2,151,980
          SECTION (B): OTHER ELECTRICAL ITEMS
          (i) Generator 62.5 KVA capacity Lump sum 00
          (ii) Supply Charges of MSEDCL (MSEB) Lump sum 00
          (iii) External Area Lighting Lump sum 00
          (iv) Solar Energy System / Renewal Lump sum 00
          (v) Lifts Lump sum 00
          (vi) Air Conditioning / Central Cooling Lump sum 00
          (vii) Transformer / Electric Sub-station etc. Lump sum 00
          (viii) CCTV Lump sum 00
          (ix) Any Other Electrical Item (Please Specify) Lump sum 00
          Sub-total (B) 00
          Total Electrical Sub-Total (3) = (3a)+(3b) 2,151,980
          Sub-Total (A) = 1+2+3 19,920,880
          SECTION (B): MISCELLANEOUS CIVIL ITEMS
          (i) Compound Wall & Gate (Rmt) Per Rmt 2,500,000
          (ii) Internal Road Pathway etc. Sqmt 00
          (iii) Dismantling Existing Building Per Km 1,500,000
          (iv) Parking Per Rmt 00
          (v) Retaining Wall Per Sqm 00
          (vi) Land Scraping / Gardening Lump sum 00
          (vii) Soil Investigation & Detailed Land Survey Lump sum 00
          (viii) C.C. Drain At Road Side & for Sanitary Disposal Per Km 00
          Sub-total (B) 4,000,000
          SECTION (C): OPTIONAL ITEMS
          1 Underground Water Tank for Rain Water Harvesting Lump sum 00
          2 Water Main Storage Pump House 2 Bore Well Lump sum 500,000
          3 Air Conditioning Lump sum 00
          4 Lift Installation Lump sum 00
          5 External Toilets Lump sum 00
          6 AB Room, Area Lightening, Pumps, Generators Lump sum 00
          7 CCTV Lump sum 00
          Sub-total (C) 500,000
          PROJECT COST (P) = (A+B+C) 24,420,880
          SECTION (D): OTHER PROVISIONS
          i Contingencies 4% on (P) 600,720
          ii Green Building Concept 5% on total civil cost 750,300
          iii Price Escalation 10% on (P) 2,442,088
          iv GST (Goods & Services Tax) 18% on total of (P) 4,395,758
          v Architectural Services 3 to 5% on (P) 732,626
          vi Labour Insurance 17% on (P) 244,205
          Sub-total (D) 9,166,301
          TOTAL COST OF PROJECT (TPC) = A+B+C+D ₹33,587,181
          SAY IN LAKH 335.87 Lakh

          DOCUMENTS / ENCLOSURES REQUIRED

          Attached Documentation:

          • Recapitulation Sheet (component-wise cost breakdown and estimation detail) — mandatory attachment to this GR
          • Reference Documents Cited (Not Directly Attached but Form Basis):

            1. Government Circular, Public Works Department, Ref. No. Sankirna-2019/Pr.Cr.10/Ima-2, dated 25.09.2019
            2. Government Resolution, Home Department, Ref. No. BGT-1021/Pr.Cr.259/RAU-1, dated 10.01.2023
            3. Letter from Joint Commissioner (Administration), State Excise, Mumbai, Ref. No. BLD112021/I.Du/Saha, dated 09.01.2024

            4. WHO IS AFFECTED

              Direct Beneficiary:

              • Inspector, State Excise Department, Gondia office — will use the newly constructed administrative building
              • Administrative/Implementation Authorities:

                1. Commissioner, State Excise, Maharashtra State, Mumbai
                2. Superintendent, State Excise, Gondia
                3. Divisional Deputy Commissioner, State Excise, Nagpur
                4. Chief Engineer, Public Works Department (PWD), Regional Division, Nagpur
                5. Executive Engineer, Public Works Department, Gondia
                6. Principal Accountant General — Maharashtra 1 (Audit/Accounts & Entitlement), Mumbai/Nagpur
मराठी अनुवाद (Marathi Translation)
गृह निभाग),

Sign in to continue reading

15 days of full content access — every Act, Rule, Regulation, GR, notification and Ex-DC-authored guide. No card required.
पूर्ण मजकूर पाहण्यासाठी साइन इन करा

Sign in with Google Already have an account? Sign in

मराठीत सारांश

# थोडक्यात:

गोंदिया येथील **उत्पादन शुल्क विभाग** (Excise Department) च्या नवीन administrative building साठी **₹3,35,87,181** (३ करोड ३५ लाख ८७ हजार) मंजूरी दिली गेली आहे.

---

## विस्तारित समजावणी

**काय बदलले?**

गोंदिया येथे **Inspector, State Excise** चे office आहे. जुनी building बिघडली (खराब झाली), म्हणून नई building बनवायची आहे. **Jayastambh Chowk, Gondia** या जागेवर हीच नई building बनवायची आहे.

**खर्च कितला?**

- **एकूण खर्च: ₹3,35,87,181 (३.३६ करोड रुपये)**

**काय काय समाविष्ट आहे?**

✓ नई administrative building (Taluka level office)
✓ Furniture — मेज, खुर्च्या इत्यादी
✓ Water supply & sanitary work
✓ Electrical work (lights, wiring)
✓ Fire safety system
✓ Compound wall & gate
✓ जुनी building पाडणे
✓ Water tank & बोरवेल (२)
✓ Contingency (अप्रत्याशित खर्च साठी) — 4%
✓ Green building concept
✓ Price escalation (10%)
✓ GST (18%)
✓ Architectural services

**काय मंजूर नाही?**

✗ Lift/Elevator
✗ Air conditioning
✗ CCTV
✗ Solar panel
✗ Generator
✗ आणि अनेक ऐच्छिक आयटम्स

**कोण वापरणार?**

गोंदिया येथील Inspector, State Excise office.

**कोण बनवणार?**

**Public Works Department (PWD), Gondia** — तर **State Excise Department** coordinate करणार.

**बजेट कोणत्या शीर्षकातून?**

- Demand No. **H-8**
- Account Head: **4059** — Public Works Capital Expenditure
- Sub-head: **Excise & State Excise Duty**

---

**महत्वाचे:** हा सिर्फ **administrative sanction** आहे. खर्चासाठी पैसे मंजूर झाले आहेत. आता PWD ला tender प्रक्रिया करून खरेदी (construction) करायचे आहे.

Original Document

Share: WhatsApp
Disclaimer: This page presents a research-grade plain-language summary of a Government of Maharashtra notification, generated by MyExcise's AI from the original government source. It is not a substitute for the original document or legal advice. Always verify the original PDF (linked above) before acting. MyExcise is a research and reference tool, not a law firm.
Link copied to clipboard!
Ask MyExcise AI MyExcise AI