What This Document Says

MAHARASHTRA EXCISE OFFICIAL DOCUMENT ANALYSIS

Document Type: Government Resolution (Shasan Niyrnay) – Administrative Sanction for Infrastructure Project

Reference Number: GR No. BGT-1024/Pr.Cr.187/RAUSHU-1

Issued By: Government of Maharashtra, Home Department (Grah Vibhag)

Date of Issue: 03 July 2024

Effective Date: From date of publication (digital signature dated as per GR)

Digital Reference Code: 202407031815402029

Location/Jurisdiction: Mauze Watole, Taluka Patan, District Satara, Maharashtra


SUMMARY

This Government Resolution grants administrative sanction for the construction of an independent/separate Maharashtra State Excise Training Academy at Watole, Taluka Patan, District Satara. The project involves construction on a total land area of 19.16 hectares (14.30 Ha in Group No. 67 and 4.86 Ha in Group No. 75) with a total sanctioned project cost of ₹93.34 crore (Nine Crore Thirty-Four Lakhs only). The construction is to be executed by the Public Works Department (PWD) with a private architect engaged. The resolution lays out specific conditions regarding architectural compliance, solar system installation, land transfer clearances, and budget allocation under the State Excise Department's capital works head.


KEY PROVISIONS

Administrative Authority & Policy Decision

  1. Administrative Sanction Granted: Full administrative sanction is provided for the construction of a dedicated/independent Training Centre for the State Excise Department (Maharashtra Rajya Utpadana Shulk Vibhag) at the specified location.

  2. Authority Cited: This sanction is granted under the powers delegated to the administrative department as per:

    • Financial Powers Rule Book, 1978, Part-I, Sub-Section Five, Item No. 1
    • Maharashtra Public Works Rules, Section 134
    • Authority delegated to the administrative department for grant of approval for capital works
    • Approving Authority: The sanction is granted under the orders and in the name of the Governor of Maharashtra.

    • Approving Official: Ravindra Aute, Deputy Secretary, Government of Maharashtra (सहपत्र - Sahapatra signature authority)


      Land Details

      1. Total Land Area: 19.16 hectares (19.16 Ha)

        • Group No. 67: 14.30 Ha (out of 14.86 Ha total in that group)
        • Group No. 75: 4.86 Ha (out of 10.84 Ha total in that group)
        • Land Status: Land availability confirmed as "Yes"

        • Land Transfer: Land transfer has been approved by:

          • Revenue & Forest Department (Mahisul va Van Vibhag) under Reference/Letter No. 03/24/J-5-A dated 04 April 2024
          • Public Works Department consent: Reference No. 12/2024/IMA-1 dated 24 June 2024 (as per decision of Higher Officers' Committee meeting dated 26 June 2024 chaired by the Chief Secretary)

          • Project Specifications & Built-Up Area

            1. Total Built-Up Area: 16,946.31 Square Metres

            2. Major Components of Construction:

              A) Main Training Academy Building – Administrative & Academic Wing, Model Excise Station

              Component Floor Area (Sq.M) Rate per Sq.M (₹) Cost (₹)
              Building Proper
              Ground Floor Ground 3,275.88 28,000 91,724,640
              First Floor First 2,258.49 28,000 63,237,720
              Second Floor Second 373.51 28,000 10,458,280
              Auditorium (200 Seating Capacity)
              Ground Floor Ground 775.99 28,000 21,727,720
              Library
              Ground Floor Ground 775.99 28,000 21,727,720
              First Floor First 518.79 28,000 14,526,120
              VIP Guest Room
              Ground Floor Ground 601.03 28,000 16,828,840
              Staff Quarters – Class 3 (Type II Quarters: 12 units, 52.8 Sq.M per flat + 10% amenities)
              Ground Floor Ground 270.11 28,000 7,563,080
              First Floor First 265.20 28,000 7,425,600
              Second Floor Second 265.20 28,000 7,425,600
              Third Floor Third 265.20 28,000 7,425,600
              Staff Quarters – Class 2 (Type III Quarters: 4 units, 60.0 Sq.M per flat + 10% amenities)
              Ground Floor Ground 160.95 28,000 4,506,600
              First Floor First 155.75 28,000 4,361,000
              Second Floor Second 155.75 28,000 4,361,000
              Staff Quarters – Class 1 (Type IV Quarters: 2 units, 92.4 Sq.M per flat + 10% amenities)
              Ground Floor Ground 200.00 28,000 5,600,000
              Ground Floor (Second Set) Ground 200.00 28,000 5,600,000
              Training Hostel – Male (100 Students: 26 Rooms, 2 Students per Room)
              Ground Floor Ground 1,872.08 28,000 52,418,240
              First Floor First 1,872.08 28,000 52,418,240
              Training Hostel – Female (48 Students: 12 Rooms, 2 Students per Room)
              Ground Floor Ground 906.18 28,000 25,373,040
              First Floor First 906.18 28,000 25,373,040
              Canteen/Dining Hall/Mess
              Ground Floor Ground 684.75 28,000 19,173,000
              Main Entrance/Exit Gate & Security Cabin
              Ground Floor Ground 187.20 28,000 5,241,600
              SUBTOTAL (A1) ₹474,496,680
            3. Component B – Electrification, Fire-Fighting, Utilities & Amenities

              Item Calculation Basis Cost (₹)
              Internal Electrification 5% of (A1) 23,724,834
              External Electrification 6% of (A1) 28,469,800.80
              Fire Fighting Arrangements etc. @₹400/Sq.M 13,557,048
              Pump House, Borewell etc. Lump Sum 2,000,000
              Air Conditioning Lump Sum 10,000,000
              CCTV Lump Sum 2,000,000
              AB Room, Area Lighting, Pumps, Generator Lump Sum 5,000,000
              Lifts 2 units @ ₹2,000,000 each 4,000,000
              MSEDCL Provisions Lump Sum 1,000,000
              SUBTOTAL (B2) ₹89,751,682.80
            4. Component C – Water Supply & Sanitary Works

              Item Calculation Basis Cost (₹)
              Water Supply & Sanitary Works 5% of (A1) 23,724,834
              SUBTOTAL (C3) ₹23,724,834
            5. Component D – Furniture

              Item Unit Quantity Rate (₹) Cost (₹)
              Furniture Sq.M 11,862.42 5,000 59,312,085
              SUBTOTAL (C4) ₹59,312,085
            6. Component E – Miscellaneous Items (Sub-Total B)

              Item Calculation Basis Cost (₹)
              Compound Wall & Gate Lump Sum 50,000,000
              Internal Roads, Land Development, Parking, Paver Block, CC Drains, C/D Works etc. As per details 21,352,350.60
              Retaining Wall Lump Sum 10,000,000
              SUBTOTAL (B) ₹81,352,350.60
            7. Component F – Contingencies, GST, Price Escalation, PMC Charges, Labour Insurance (Sub-Total C)

              Item Calculation Basis Cost (₹)
              Contingencies 4% of (A1) Subtotal 18,979,867.20
              GST 18% on (P) = 18% of Project Cost 131,154,773.80
              Price Escalation 5% on (P) = 5% of Project Cost 36,431,881.62
              PMC Charges 1.5% on (P) = 1.5% of Project Cost 10,929,564.49
              Labour Insurance 1% on (P) = 1% of Project Cost 7,286,376.32
              SUBTOTAL (C) – Provisions ₹204,782,463.43

              TOTAL PROJECT COST CALCULATION

              Item Cost (₹)
              (A) Building, Electrification, Water Supply, Furniture 647,285,282
              (B) Miscellaneous Items 81,352,350.60
              Subtotal (A+B) 728,637,632.60
              (C) Contingencies, GST, Price Escalation, PMC, Labour Insurance 204,782,463.43
              TOTAL PROJECT COST (TPC) ₹933,420,095.99
              Rounded / Sanctioned as ₹93.34 Crore (Nine Crore Thirty-Four Lakhs)

              Construction Unit Cost Metrics

              1. Cost per Square Metre:
                • Building Civil (A1): ₹28,000/Sq.M
मराठी अनुवाद (Marathi Translation)
सहपत्र - रविद्र औटे) उप सचिव, महाराष्ट्र शासन) जुलै, 2024)

Sign in to continue reading

15 days of full content access — every Act, Rule, Regulation, GR, notification and Ex-DC-authored guide. No card required.
पूर्ण मजकूर पाहण्यासाठी साइन इन करा

Sign in with Google Already have an account? Sign in

मराठीत सारांश

# थोडक्यात:

महाराष्ट्र सरकारने सातारा जिल्ह्यातील वाटोळे गावात राज्य उत्पादन शुल्क विभागासाठी नवीन प्रशिक्षण केंद्र बांधण्यास मंजुरी दिली. खर्च ₹93.34 कोटी, जमीन 19.16 हेक्टर.

---

## विस्तृत माहिती:

**काय मंजूर झाले?**
- सातारा जिल्ह्यातील वाटोळे गावात उत्पादन शुल्क विभागाचे स्वतंत्र प्रशिक्षण केंद्र बांधणे
- हा महाराष्ट्र सरकारच्या Home Department ने 3 जुलै 2024 ला मंजूर केला

**बांधकाम कसले असेल?**

| **सुविधा** | **माहिती** |
|---|---|
| **जमीन** | 19.16 हेक्टर (वाटोळे, पाटण, सातारा) |
| **बांधकामाचा क्षेत्र** | 16,946 चौरस मीटर |
| **एकूण खर्च** | ₹93.34 कोटी |
| **हॉस्टेल (मुलांसाठी)** | 100 विद्यार्थी |
| **हॉस्टेल (मुलींसाठी)** | 48 विद्यार्थी |
| **Auditorium** | 200 लोकांची क्षमता |
| **कर्मचारी क्वार्टर** | 18 घरे (वेगवेगळ्या श्रेणीमध्ये) |
| **लायब्रेरी** | 2 मजल्यांची |
| **कॅन्टीन** | शिक्षकांव कर्मचार्यांसाठी |

**कोण बांधणार?**
- सार्वजनिक बांधकाम विभाग (PWD)
- खाजगी आर्किटेक्ट नियुक्त केला गेला

**खर्चाची विभागणी:**

| **मद** | **खर्च** |
|---|---|
| इमारत (मुख्य भाग) | ₹47.45 कोटी |
| विजेचे काम, पाणी, फर्निचर | ₹16.79 कोटी |
| रस्ते, कंपाउंड वॉल, इतर काम | ₹8.14 कोटी |
| Contingency, GST, वाढ | ₹20.47 कोटी |

**महत्वाचे शर्ती:**

1. **सौर ऊर्जा (Solar System) अनिवार्य:**
- सूर्यास्ताळ्यातून वीज तयार करण्यासाठी सोलर पॅनेल लावायचे
- Excise Commissioner जबाबदार आहेत

2. **आर्किटेक्चर शासनाच्या नियमांनुसार:**
- Private architect ने PWD/Govt. के मानदंड पाळायचेत
- शासन आर्किटेक्टची मंजुरी आवश्यक

3. **जमीन मिळ गेली:**
- Revenue व Forest Dept.ने मंजुरी दिली (4 एप्रिल 2024)
- PWD ने बांधकामाची मंजुरी दिली (24 जून 2024)
- कोणत्या delay नाहीत

**बजेट कोडः**
खर्च महाराष्ट्र सरकारच्या 4059-1033 budget head मधून होणार (Public Works खाती, Excise Department).

**केव्हा सुरु होणार?**
3 जुलै 2024 पासून ही मंजुरी लागू आहे.

---

**सरल भाषेत:** शासनाने सातारा जिल्ह्यातील एक नवीन दारू विभाग प्रशिक्षण केंद्र बांधायचे ठरवले. यात छात्रावास, लायब्रेरी, Auditorium, कर्मचारी घरे असतील. ₹93 कोटी खर्च होणार. PWD बांधकाम करणार.

Original Document

Share: WhatsApp
Disclaimer: This page presents a research-grade plain-language summary of a Government of Maharashtra notification, generated by MyExcise's AI from the original government source. It is not a substitute for the original document or legal advice. Always verify the original PDF (linked above) before acting. MyExcise is a research and reference tool, not a law firm.