अधीक्षक, राज्य उत्पादन शुल्क, नंदुरबार कार्यालयाची नवीन प्रशासकीय इमारत, संरक्षक भिंत, अंतर्गत रस्ते यांचे बांधकाम करिता सुधारित प्रशासकीय मान्यता प्रदान करणेबाबत.

Reference
202505071630473029
Issued
07 May 2025
Source
GR Portal (Home Dept - State Excise)
Category
Gr Home Dept

What This Document Says

Amended Rule/Section: State Excise Department Administrative Approval — GR No. BGT-1023/Pr.Cr.52/RAUSHU-1

Type of Change: Revised Administrative Approval (Substitution of Earlier Sanction)

What Changed:

The Government of Maharashtra Home Department has issued revised administrative approval for the construction of a new administrative building, boundary wall, and internal roads for the Office of the Superintendent, State Excise, Nandurbar. The original administrative approval (dated 28 February 2023) sanctioned construction at ₹8,93,10,000. This revised approval increases the sanctioned budget to ₹9,63,63,000 (Nine crore sixty-three lakh sixty-three thousand rupees). The revision was necessitated because: (1) access road to the approved plot was unavailable, requiring an internal approach road of approximately 100 metres within the plot boundary; and (2) the site being on sloping terrain with steep gradients required a change in building design from G+1 (Ground + 1 storey) to Stilt Floor + 2 storeys for safety reasons. Revised architectural plans were prepared by the Deputy Chief Architect, Public Works Department, and approved by competent authorities.

Key Details:

  • Original Sanction: ₹8,93,10,000 (GR dated 28 February 2023)
  • Revised Sanction: ₹9,63,63,000
  • Budget Increase: ₹70,53,000
  • Location: Holi Tappa Haveli, Tal. Raj. Nandurbar — S.No. 100/1-A (1.00 hectare out of 21.19 hectares), government land under State Excise Department control
  • Major Cost Components:
    • Building construction: ₹64,894,932.11
    • Furniture: ₹6,000,000
    • GST (18%): ₹12,871,304
    • Electrification (11%): ₹7,138,443
    • Labour & Asset Insurance (1% each): ₹708,949 each
    • Water supply (2%): ₹1,297,899
    • Contingencies (2%): ₹1,430,145
    • Fire-fighting arrangements: ₹700,000
  • Design Change: G+1 → Stilt Floor + 2 storeys
  • Budget Head: Public Works Department (H-8, 4059) — Capital Works for Excise Department; Major Buildings (Programme 4059-1033), Major Buildings
  • Authority: Financial Rules, 1978; Maharashtra Public Works Manual; Para 134(1)

Effective Date: 7 May 2025 (date of publication)

Authority: Maharashtra Home Department; issued under the authority delegated to the Administrative Department by the Financial Authority Rules, 1978 and Maharashtra Public Works Manual

Original Document

Disclaimer: This page presents a research-grade plain-language summary of a Government of Maharashtra notification, generated by MyExcise's AI from the original government source. It is not a substitute for the original document or legal advice. Always verify the original PDF (linked above) before acting. MyExcise is a research and reference tool, not a law firm.