Document Type: Government Resolution (Shasan Nirnay) — Administrative Approval for Capital Construction Project
Reference Number: GR No. BJT-1023/Pr.Kr.75/RAUSH-1
Issued By: Government of Maharashtra, Home Department (Griha Vibhag), Ministry, Mumbai-400 032
Effective Date: 24 April 2023 (Nidank: 24 April, 2023)
Digital Reference Code: 202304241717514129
This Government Resolution grants administrative approval for the construction of a new administrative building and staff residential quarters at the State Excise Inspector's office in Chopda, Tal. Jalgaon. The project is sanctioned at a total cost of ₹4,58,90,000 (Four crore fifty-eight lakhs ninety thousand rupees only). The approval is issued under the Financial Authority Handbook 1978 (Part-I, Sub-section 5) and Maharashtra Public Works Rules, Para 134. The construction will be funded from the capital expenditure head "4059 - Capital Expenditure on Public Works" under the Excise and State Excise Department. The resolution is issued in compliance with Public Works Department consent and is digitally signed.
(A) ESSENTIAL ITEMS
1(a) Building Proper (Built-Up Area)
| Component | Area | Unit Rate | Cost (₹) |
|---|---|---|---|
| Excise Office Building — Ground Floor | 477.49 Sq. M | 28,000 | 13,369,720 |
| Residential Quarters — Type III (Ground Floor) | 80.96 Sq. M | 28,000 | 2,266,880 |
| Residential Quarters — Type II (Ground Floor) | 270.41 Sq. M | 28,000 | 7,571,480 |
| Residential Quarters — Type II (First Floor) | 82.06 Sq. M | 28,000 | 2,297,680 |
| Total Built-Up Area (B.U.A.) | 910.92 Sq. M | — | Sub-Total: ₹25,505,760 |
1(b) & (c) Ancillary Works
| Item | Rate/Basis | Cost (₹) |
|---|---|---|
| Rain/Roof Water Harvesting System | Lump Sum | 500,000 |
| Furniture (70% of BUA @ ₹5,000 per unit) | 509 units × ₹5,000 | 2,545,000 |
| Sub-Total (1b + 1c) | — | ₹3,045,000 |
2. Water Supply & Sanitary Works