Document Type: Government Resolution (GR) — Administrative Sanction for Capital Works
Reference Number: GR No. BJT-1021/Pr.Cr.53/RAUSHU-1, dated 15 November 2021
Issued By: Home Department (गृह विभाग), Government of Maharashtra
Effective Date: 15 November 2021
Digital Reference Code: 202111151552138929
This Government Resolution grants administrative sanction for the construction of a new office building for the Superintendent of State Excise (अधीक्षक, राज्य उत्पादन शुल्क), Solapur. The project involves construction of a stilt + G+2 storey administrative building on Plot No. 145/A, Railway Line, Solapur, spanning 3,597.12 square meters. The total project cost is sanctioned at ₹15,93,45,974 (Fifteen Crore Ninety-Three Lakh Forty-Five Thousand Nine Hundred Seventy-Four only). The sanction is issued following approval from the High-Power Committee chaired by the Chief Secretary, and with concurrence from the Public Works Department and Finance Department.
| Sr. No. | Particulars | Unit | Rate/Norm | Amount (₹) |
|---|---|---|---|---|
| 1(a) | Building Proper (Built-Up Area) | 3,597.12 Sq.M | ₹23,000 per Sq.M | 8,27,33,760 |
| 1(b) | Fuel Gas Pipeline | — | — | 0 |
| 1(c) | Bio-Diesel | — | — | 0 |
| 1(d) | Rain/Roof Water Harvesting | LS | — | 5,00,000 |
| 1(e) | Solar Rooftop (MOU execution) | — | — | 0 |
| 1(f) | Ramp for Handicaps | LS | — | 30,000 |
| 1(g) | Furniture (2,161 Sq.M @ 70% of 3,087.62) | — | ₹5,000 per Sq.M | 1,08,06,670 |
| Subtotal Essential Items (A) | — | — | — | ₹11,23,36,670 |
| 2 | Water Supply & Sanitary Works | 5% of (1a) | — | ₹41,36,688 |
| 3(a) | Electrification (Internal) | 5% of (1a) | — | ₹41,36,688 |
| 3(b) | Electrification (External) | 6% of (1a) | — | ₹49,64,026 |
| 3(c) | Fire Fighting Arrangements etc. | LS | — | ₹50,00,000 |
| Subtotal Item 2 & 3 | — | — | — | ₹1,41,00,714 |
| Subtotal (A) | — | — | — | ₹1,12,30,78,32 |
| MISCELLANEOUS ITEMS (B) | — | — | — | — |
| (i) | Compound Wall & Gate | 471.91 Rmt | ₹8,000 per Rmt | ₹37,75,280 |
| (ii) | Internal Roads | 776.97 Rmt | ₹8,000 per Rmt | ₹62,15,760 |
| (iii) | Development of Ground, Horticulture | — | — | 0 |
| (iv) | Parking | LS | — | ₹5,00,000 |
| (v) | Retaining Wall | — | — | 0 |
| (vi) | Landscaping | LS | — | ₹2,00,000 |
| (vii) | Soil Investigations & Detail Land Survey | LS | — | 0 |
| (viii) | CC Drains and CI Works | LS | — | 0 |
| (ix) | Dismantling of Old Building | LS | — | ₹2,00,000 |
| Subtotal (B) | — | — | — | ₹1,08,91,040 |
| OPTIONAL ITEMS (C) | — | — | — | — |
| 1 | Underground Water Tank for R/W Harvesting | Cu.M | — | ₹5,00,000 |
| 2 | Water Main Storage, Pumphouse, Borewell | — | — | ₹5,00,000 |
| 3 | Air Conditioning | — | — | 0 |
| 4 | Lifts | — | — | ₹20,00,000 |
| 5 | External Toilets | — | — | ₹2,00,000 |
| 6 | AB Room, Area Lighting, Pumps, Generator | — | — | ₹10,00,000 |
| 7 | CCTV | — | — | ₹5,00,000 |
| 8 | Gardening/Plantation of Trees | — | — | 0 |
| Subtotal (C) | — | — | — | ₹47,00,000 |
| Project Cost (A+B+C) | — | — | — | ₹1,27,89,89,872 |
| PROVISIONS (D) | — | — | — | — |
| (i) | Contingencies @ 4% on (A) | — | — | ₹33,09,350 |
| (ii) | GST @ 12% on (A+B+C) | — | — | ₹1,53,47,865 |
| (iii) | Price Escalation @ 10% on Project Cost (P) | — | — | ₹12,78,98,872 |
| Subtotal (D) | — | — | — | ₹31,44,71,102 |
| TOTAL COST OF PROJECT (A+B+C+D) | — | — | — | ₹1,59,34,59,974 |
In words: Fifteen Crore Ninety-Three Lakh Forty-Five Thousand Nine Hundred Seventy-Four rupees only.