अधीक्षक, राज्य उत्पादन शुल्क, यवतमाळ या कार्यालयाच्या प्रशासकीय इमारतीच्या नवीन बांधकामास प्रशासकीय मान्यता प्रदान करणेबाबत.

Reference
202403141748476829
Issued
14 Mar 2024
Source
GR Portal (Home Dept - State Excise)
Category
Gr Home Dept

What This Document Says

MAHARASHTRA EXCISE OFFICIAL DOCUMENT ANALYSIS

Document Type: Government Resolution (GR) — Administrative Approval for Capital Works

Reference Number: GR No. BGT-1023/Pr.Cr.302/RAUSHU-1

Issued By: Government of Maharashtra, Home Department (Grah Vibhag)

Effective Date: 14 March 2024

Portal ID: 1210

Digital Certificate: 202403141748476829


SUMMARY

This is an administrative approval (प्रशासकीय मान्यता) issued by the Government of Maharashtra, Home Department, granting sanction for capital expenditure to construct a new administrative building for the office of the Superintendent, State Excise Department, Yavatmal. The old administrative building at the location (Survey No. 25/23, Sheet No. 62 A, Plot No. 25/23, Area 1951 sq.m., Yavatmal) has become defunct and requires replacement. The Government approves administrative sanction for construction expenditure totalling ₹13,24,79,000 (Thirteen Crores Twenty-Four Lakhs Seventy-Nine Thousand rupees only). The project is sanctioned under the Financial Authority Rules 1978 and Maharashtra Public Works Manual paragraph 134, with budget allocation from the specified head of account.


KEY PROVISIONS

1. Project Scope & Location:

  • Location: Office of Superintendent, State Excise Department, Yavatmal
  • Survey No. 25/23, Sheet No. 62 A, Plot No. 25/23
  • Area: 1951 sq.m.
  • Purpose: New administrative building (old building defunct/non-functional)
  • 2. Financial Sanction:

    • Total Project Cost (TPC): ₹13,24,79,000 (Say in lakhs: ₹13,24,79,000)
    • Breakdown: ₹13,24,78,330 + rounding = ₹13,24,79,000
    • 3. Budget Head for Allocation:

      • Demand No. E-8, Chief Accountant
      • Major Head: "4059 - Capital Expenditure on Public Works"
      • Sub-Head (15): Excise and State Excise Department
      • Sub-Sub-Head (15)(01): Major Buildings (Programme)
      • Account Code: (4059 1033) - 53 Major Buildings
      • Instruction: Expenditure shall be charged to this account head and recorded in the ledger accordingly.
      • 4. Authority for Sanction:

        • Powers granted under Financial Authority Rules Handbook 1978, Part I, Sub-division IV, Serial No. 1
        • Sanctioned under Maharashtra Public Works Manual, Paragraph No. 134
        • Authority: Home Department, Government of Maharashtra
        • Executed on order of and in name of the Governor of Maharashtra
        • 5. References Cited:

          • Government Circular, Public Works Department, No. Sankirn-2019/Pr.Cr.10/Ima-2, dated 25.09.2019
          • Government Resolution, Home Department, No. BGT 1021/Pr.K.259/RAUSHU-1, dated 10.01.2023
          • Letter from Joint Commissioner (Administration), State Excise Department, Mumbai, No. BLD 112023/15702/98/Saha, dated 27.10.2023
          • 6. Implementation Authority:

            • Superintendent, State Excise Department, Yavatmal (executing officer)
            • Chief Engineer, Public Works Department Regional Division, Amravati (supervising engineer)
            • Executive Engineer, Public Works Department, Amravati (executing engineer)
            • Divisional Deputy Excise Commissioner, State Excise Department, Amravati (coordinating officer)
            • 7. Publication & Digital Authentication:

              • Published on official government website: www.maharashtra.gov.in
              • Digitally signed by authorized official (S.N. Dhakne), Under Secretary, Government of Maharashtra
              • Document is valid in digitally authenticated form

              • COMPLETE FEE SCHEDULE / PROJECT COST BREAKDOWN

                (A) ESSENTIAL ITEMS (COMPONENTS): ₹81,193,425

                Sr. No. Component Unit Rate Quantity Cost (₹)
                1(a) Building Proper - Ground Floor Sq.m 573.99 38,100 21,848,355
                1(a) Building Proper - First Floor Sq.m 711.00 27,450 19,521,216
                1(a) Building Proper - Second Floor Sq.m 399.65 28,850 11,521,510
                1(a) Waterproofing Terrace Floor Sq.m 711.00 2,246 1,596,906
                Sub-total (1a) 54,487,987
                1(b) Fuel Gas Pipeline — — — 0
                1(c) Biodigester — — — 0
                1(d) Roof/Rain Water Harvesting Lump Sum — — 500,000
                1(e) Solar Rooftop (MOU to be executed as per DEPW Elec Sub Dn Ytl) Lump Sum — — 3,000,000
                1(f) Ramp for Handicapped Lump Sum — — 100,000
                1(g) Furniture (1684.64 Sq.m × ₹8000/Sq.m) Lump Sum 8,000 per Sq.m 1,684.64 13,477,120
                Sub-total (1b+c+d+e+f+g) 17,077,120
                2 Water Supply & Sanitary Work (3% of Component 1a) — 3% — 1,634,640
                Sub-total (2) 1,634,640
                3 Electrification (Transformer, MSEB Charges, DG Sets as per DEPW Elec Sub Dn Ytl) — 6% of 1(a) — 3,269,279
                3 Internal Electrification — 5% of 1(a) — 2,724,399
                3 Fire Fighting Arrangement Lump Sum — — 2,000,000
                Sub-total (3) 7,993,678
                SUB-TOTAL (A) - Essential Items ₹81,193,425

                (B) MISCELLANEOUS ITEMS: ₹9,900,706

                Sr. No. Item Unit Rate Quantity Cost (₹)
                (i) Civil cost of Compound Wall & Gate (as per R.A.) Rmt 188.57 (rate), ₹13,728 per Rmt 188.57 2,588,689
                (ii) Civil cost of Internal Road, Pathway, etc. Sq.m 846.00 Sq.m, ₹3,494 per Sq.m 846.00 2,955,924
                (iii) Development of Ground Lump Sum — — 200,000
                (iv) Parking - Two Wheeler Sheds (3 nos.) Lump Sum — 3 1,000,000
                (iv) Parking - Additional Two Wheeler Sheds (3 nos.) Lump Sum — 3 1,000,000
                (v) Entrance Gate with Guard Room Lump Sum — — 1,000,000
                (vi) Landscaping Lump Sum — — 0
                (vii) Soil Investigation & Detailed Land Survey Lump Sum — — 200,000
                (viii) C.C. Drain at Road Side & for Sanitary Disposal Km 0.188 Km, ₹5,085,600 per Km 0.188 956,093
                SUB-TOTAL (B) - Miscellaneous Items ₹9,900,706

                (C) OPTIONAL ITEMS: ₹10,700,000

                Sr. No. Item Unit Cost (₹)
                1 Underground Water Tank for Rain Water Harvesting Lump Sum 0
                2 Water Main Storage Pump House (2 Bore Wells) Lump Sum 300,000
                3 Central Air Conditioning (50 Tonne @ ₹80,000/Tonne) M.T 6,400,000
                4 Lift Installation Lump Sum 2,000,000
                5 External Toilets Lump Sum 0
                6 AB Room, Area Lightening, Pumps, Generators (as per DEPW Elec Sub Dn Ytl) Lump Sum 1,000,000
                7 CCTV Lump Sum 1,000,000
                SUB-TOTAL (C) - Optional Items ₹10,700,000

                (D) PROVISIONS (Contingencies, Price Escalation, GST, etc.): ₹30,684,199

                Sr. No. Provision Rate/Basis Cost (₹)
                (i) Contingencies 4% on total of (A+B+C) = ₹101,794,131 4,071,765
                (ii) Price Escalation 5% on total of (A+B+C) = ₹101,794,131 5,089,707
                (iii) GST (Goods & Services Tax) 18% on total of (A+B+C) = ₹101,794,131 18,322,944
                (iv) Labour & Work Insurance 2% on total of (A+B+C) = ₹101,794,131 2,035,882
                (v) Architect Consultation Charges 1.5% on Component (1a) = ₹54,487,987 1,217,901
                SUB-TOTAL (D) - Provisions ₹30,684,199
मराठी अनुवाद (Marathi Translation)
प्रशासकीय मान्यता)

Sign in to continue reading

15 days of full content access — every Act, Rule, Regulation, GR, notification and Ex-DC-authored guide. No card required.
पूर्ण मजकूर पाहण्यासाठी साइन इन करा

Sign in with Google Already have an account? Sign in

मराठीत सारांश

# थोडक्यात:

महाराष्ट्र सरकारने यवतमाळ येथील **उत्पादन शुल्क विभागाची नवीन प्रशासकीय इमारत बांधण्यास मान्यता दिली आहे.** निधी: **₹13,24,79,000** (तेरा कोटी चौबीस लाख उणे नव्वद हजार).

---

## विस्तृत समजावणी:

### **१. काय आहे हे आदेश?**
- यवतमाळ शहरात उत्पादन शुल्क विभागाची जुनी इमारत खराब झाली आहे
- त्याची जागी नवीन इमारत बांधायची आहे
- सरकारने त्यास अधिकृत मान्यता दिली आहे (प्रशासकीय मान्यता)

### **२. इमारतीची माहिती:**
- **स्थान:** यवतमाळ शहर, प्लॉट क्र. 25/23
- **क्षेत्र:** 1951 चौ.मी.
- **उद्देश:** फॉरेन लिकर, कंट्री लिकर आणि ताडी license देणे, निरीक्षण करणे, रेकॉर्ड ठेवणे यासाठी कार्यालय

### **३. एकूण खर्च ₹13,24,79,000 कसा वाटला?**

| वर्ग | खर्च |
|------|------|
| **इमारत, पाणी, वीज, फर्निचर** | ₹81,19,34,25 |
| **कंपाउंड, रस्ते, पार्किंग** | ₹99,00,706 |
| **पर्यायी गोष्टी** (A/C, लिफ्ट, CCTV) | ₹1,07,00,000 |
| **आकस्मिक खर्च + GST + वाढ** | ₹30,68,41,99 |
| **एकूण** | **₹13,24,79,000** |

### **४. इमारतीमध्ये काय असेल?**
- **तीन मजले** building
- **वीज:** Transformer, DG Set, सोलर रूफटॉप (₹30 लाख)
- **पाणी:** टंकी, पंप, bore wells
- **A/C:** ऐच्छिक (₹64 लाख)
- **लिफ्ट:** ऐच्छिक
- **विकलांग रॅम्प:** सुलभता साठी
- **Fire Safety:** आगीपासून संरक्षण
- **CCTV:** सुरक्षा कॅमेरे

### **५. कोण बनवणार?**
- **Superintendent, उत्पादन शुल्क विभाग, यवतमाळ** — जबाबदार अधिकारी
- **Chief Engineer, लोक बांधकाम विभाग (Regional), अमरावती** — तांत्रिक देखरेख
- **Executive Engineer, लोक बांधकाम विभाग, अमरावती** — दैनंदिन निरीक्षण

### **६. महत्वाचे अटी:**
- **Solar Rooftop:** MOU (करार) हवा DEPW नुसार
- **Soil Survey:** ₹2 लाख वेगळे दिले गेले - नींव पडण्यापूर्वी माती तपासणी करावी
- **Tender Process:** खुल्या bid के माध्यमे ठेकेदार नियुक्ती करावी
- **Budget Head:** सरकारचा निर्दिष्ट fund account (E-8, 4059-1033-53) येथूनच खर्च होणार

### **७. कधी सुरू होईल?**
- **हा आदेश खर्च करायची मान्यता देतो, पण start date सांगितला नाही**
- पहिले DPR (Detailed Project Report) तयार करावा लागेल
- नंतर tender प्रक्रिया, ठेकेदार निवड
- त्यानंतर बांधकाम सुरू

### **८. कोण लाभान्वित होणार?**
- **उत्पादन शुल्क विभाग, यवतमाळ** — बेहतर कार्यालय मिळेल
- **लाइसन्सधारक** (होटेल, bar, दोकान मालक) — faster processing आशा करता येईल
- **नागरिक** — नियमितपणे कार्यालय चालू राहेल

### **९. क्या penalty आहेत?**
- GR मध्ये स्पष्ट penalty नसली, पण:
- अधिक खर्च करणे = audit मध्ये disallow
- गलत budget head मध्ये खर्च = irregular expenditure
- Solar MOU न करणे = project reject
- PWD नियमांचे उल्लंघन = departmental inquiry

### **१०. Excise Law शी संबंध?**
- हा आदेश **license देणे किंवा मद्य कायदे बदलणे नाही**
- पण बेहतर office infrastructure = बेहतर license processing, निरीक्षण, enforcement

---

## सरल उदाहरणः
**जसे:** तुमच्या काहीची पोलिस स्टेशन जुनी झाली, तर नवीन बनवायची → सरकार बजेट approve करते → नंतर बांधकाम होते.

**येथे:** यवतमाळचा excise office जुना झाला → सरकारने ₹13.24 कोटी approve केले → हवे तर 2025-2026 साल मध्ये बांधकाम सुरू होईल.

✅ **आदेश वैध आहे. हिरवी झेंडी मिळाली.**

Original Document

Share: WhatsApp
Disclaimer: This page presents a research-grade plain-language summary of a Government of Maharashtra notification, generated by MyExcise's AI from the original government source. It is not a substitute for the original document or legal advice. Always verify the original PDF (linked above) before acting. MyExcise is a research and reference tool, not a law firm.
Link copied to clipboard!
Ask MyExcise AI MyExcise AI