Document Type: Government Resolution (GR) — Administrative Approval for Capital Works
Reference Number: GR No. BGT-1023/Pr.Cr.302/RAUSHU-1
Issued By: Government of Maharashtra, Home Department (Grah Vibhag)
Effective Date: 14 March 2024
Portal ID: 1210
Digital Certificate: 202403141748476829
This is an administrative approval (प्रशासकीय मान्यता) issued by the Government of Maharashtra, Home Department, granting sanction for capital expenditure to construct a new administrative building for the office of the Superintendent, State Excise Department, Yavatmal. The old administrative building at the location (Survey No. 25/23, Sheet No. 62 A, Plot No. 25/23, Area 1951 sq.m., Yavatmal) has become defunct and requires replacement. The Government approves administrative sanction for construction expenditure totalling ₹13,24,79,000 (Thirteen Crores Twenty-Four Lakhs Seventy-Nine Thousand rupees only). The project is sanctioned under the Financial Authority Rules 1978 and Maharashtra Public Works Manual paragraph 134, with budget allocation from the specified head of account.
1. Project Scope & Location:
2. Financial Sanction:
3. Budget Head for Allocation:
4. Authority for Sanction:
5. References Cited:
6. Implementation Authority:
7. Publication & Digital Authentication:
| Sr. No. | Component | Unit | Rate | Quantity | Cost (₹) |
|---|---|---|---|---|---|
| 1(a) | Building Proper - Ground Floor | Sq.m | 573.99 | 38,100 | 21,848,355 |
| 1(a) | Building Proper - First Floor | Sq.m | 711.00 | 27,450 | 19,521,216 |
| 1(a) | Building Proper - Second Floor | Sq.m | 399.65 | 28,850 | 11,521,510 |
| 1(a) | Waterproofing Terrace Floor | Sq.m | 711.00 | 2,246 | 1,596,906 |
| Sub-total (1a) | 54,487,987 | ||||
| 1(b) | Fuel Gas Pipeline | — | — | — | 0 |
| 1(c) | Biodigester | — | — | — | 0 |
| 1(d) | Roof/Rain Water Harvesting | Lump Sum | — | — | 500,000 |
| 1(e) | Solar Rooftop (MOU to be executed as per DEPW Elec Sub Dn Ytl) | Lump Sum | — | — | 3,000,000 |
| 1(f) | Ramp for Handicapped | Lump Sum | — | — | 100,000 |
| 1(g) | Furniture (1684.64 Sq.m × ₹8000/Sq.m) | Lump Sum | 8,000 per Sq.m | 1,684.64 | 13,477,120 |
| Sub-total (1b+c+d+e+f+g) | 17,077,120 | ||||
| 2 | Water Supply & Sanitary Work (3% of Component 1a) | — | 3% | — | 1,634,640 |
| Sub-total (2) | 1,634,640 | ||||
| 3 | Electrification (Transformer, MSEB Charges, DG Sets as per DEPW Elec Sub Dn Ytl) | — | 6% of 1(a) | — | 3,269,279 |
| 3 | Internal Electrification | — | 5% of 1(a) | — | 2,724,399 |
| 3 | Fire Fighting Arrangement | Lump Sum | — | — | 2,000,000 |
| Sub-total (3) | 7,993,678 | ||||
| SUB-TOTAL (A) - Essential Items | ₹81,193,425 |
| Sr. No. | Item | Unit | Rate | Quantity | Cost (₹) |
|---|---|---|---|---|---|
| (i) | Civil cost of Compound Wall & Gate (as per R.A.) | Rmt | 188.57 (rate), ₹13,728 per Rmt | 188.57 | 2,588,689 |
| (ii) | Civil cost of Internal Road, Pathway, etc. | Sq.m | 846.00 Sq.m, ₹3,494 per Sq.m | 846.00 | 2,955,924 |
| (iii) | Development of Ground | Lump Sum | — | — | 200,000 |
| (iv) | Parking - Two Wheeler Sheds (3 nos.) | Lump Sum | — | 3 | 1,000,000 |
| (iv) | Parking - Additional Two Wheeler Sheds (3 nos.) | Lump Sum | — | 3 | 1,000,000 |
| (v) | Entrance Gate with Guard Room | Lump Sum | — | — | 1,000,000 |
| (vi) | Landscaping | Lump Sum | — | — | 0 |
| (vii) | Soil Investigation & Detailed Land Survey | Lump Sum | — | — | 200,000 |
| (viii) | C.C. Drain at Road Side & for Sanitary Disposal | Km | 0.188 Km, ₹5,085,600 per Km | 0.188 | 956,093 |
| SUB-TOTAL (B) - Miscellaneous Items | ₹9,900,706 |
| Sr. No. | Item | Unit | Cost (₹) |
|---|---|---|---|
| 1 | Underground Water Tank for Rain Water Harvesting | Lump Sum | 0 |
| 2 | Water Main Storage Pump House (2 Bore Wells) | Lump Sum | 300,000 |
| 3 | Central Air Conditioning (50 Tonne @ ₹80,000/Tonne) | M.T | 6,400,000 |
| 4 | Lift Installation | Lump Sum | 2,000,000 |
| 5 | External Toilets | Lump Sum | 0 |
| 6 | AB Room, Area Lightening, Pumps, Generators (as per DEPW Elec Sub Dn Ytl) | Lump Sum | 1,000,000 |
| 7 | CCTV | Lump Sum | 1,000,000 |
| SUB-TOTAL (C) - Optional Items | ₹10,700,000 |
| Sr. No. | Provision | Rate/Basis | Cost (₹) |
|---|---|---|---|
| (i) | Contingencies | 4% on total of (A+B+C) = ₹101,794,131 | 4,071,765 |
| (ii) | Price Escalation | 5% on total of (A+B+C) = ₹101,794,131 | 5,089,707 |
| (iii) | GST (Goods & Services Tax) | 18% on total of (A+B+C) = ₹101,794,131 | 18,322,944 |
| (iv) | Labour & Work Insurance | 2% on total of (A+B+C) = ₹101,794,131 | 2,035,882 |
| (v) | Architect Consultation Charges | 1.5% on Component (1a) = ₹54,487,987 | 1,217,901 |
| SUB-TOTAL (D) - Provisions | ₹30,684,199 |